Abstract: A well screen is constructed by positioning a crimp ring encircling and over an end of a wrapped on pipe screen layer on a tubular base pipe. The crimp ring is plastically deformed about an outer surface of the screen layer. A bead of weld is applied to affix the crimp ring to the base pipe.

Get Free WhatsApp Updates!
Notices, Deadlines & Correspondence

Patent Information

Application #
Filing Date
21 February 2013
Publication Number
42/2014
Publication Type
INA
Invention Field
CIVIL
Status
Email
sna@sna-ip.com
Parent Application
Patent Number
Legal Status
Grant Date
2020-10-23
Renewal Date

Applicants

HALLIBURTON ENERGY SERVICES INC.
10200 Bellaire Blvd. Houston Texas 77072

Inventors

1. CUNNINGHAM Gregory Scott
532 Chasewood Drive Grapevine Texas 76051
2. LOPEZ Jean Marc
7308 Stoddard Lane Plano Texas 75025

Specification

Crimped End Wrapped On Pipe Well Screen
CROSS-REFERENCE TO RELATEDAPPLICATION
This application claims priority under 35 U.S.C. § 119 to U.S. Patent Application
Serial No. 12/855,932, filed August 13, 2010, which is herein incorporated by reference
in its entirety.
BACKGROUND
[0001] This description relates to filtration apparatus for use in subterranean wellbores.
[0002] For centuries, wells have been drilled to extract oil, natural gas, water, and other
fluids from subterranean formations. In extracting the fluids, a production string is
provided in a wellbore, both reinforcing the structural integrity of the wellbore, as well as
assisting in extraction of fluids from the well. To allow fluids to flow into production
string, apertures are often provided in the tubing string in the section of the string
corresponding with production zones of the well. Although perforations allow for ingress
of the desired fluids from the formation, these perforations can also allow unwanted
materials to flow into the well from the surrounding foundations during production.
Debris, such as formation sand and other particulate, can fall or be swept into the tubing
together with formation fluid, contaminating the recovered fluid. Not only do sand and
other particulates contaminate the recovered fluid, this particulate can cause many
additional problems for the well operator. For example, as the particulate flows through
production equipment, it gradually erodes the equipment, accumulate in chambers, and
block flow passages. Repairing and replacing production equipment damaged by
particulate in-flow can be costly and time-consuming, particularly for downhole
equipment sometimes located several thousand feet below the Earth's surface.
Consequently, to guard against particulate from entering production equipment, while at
the same time preserving sufficient fluid flow pathways, various production filters and
filtration methods have been developed and employed including gravel packs and well
screen assemblies.
[0003] A number of well screen filtration designs have been employed. A well screen
assembly is a screen of one or more layers installed in the well, capable of filtering
against passage of particulate of a specified size and larger, such as sand, rock fragments
and gravel from surrounding gravel packing. The specific design of the well screen can
take into account the type of subterranean formation likely to be encountered, as well as
the well-type.
SUMMARY
[0004] This description relates to filtration apparatus for use in subterranean wellbores,
for example, well screen assemblies.
[0005] In certain aspects, a well screen assembly has an elongate tubular base pipe
defining apertures extending between the interior and exterior of the base pipe. A screen
layer is carried on the base pipe and includes a wire that has been wrapped helically
around the exterior of the base pipe. A crimp ring is affixed to the base pipe and encircles
the base pipe and an end of the screen layer. The crimp ring is plastically deformed about
an outer surface of the screen layer.
[0006] In certain aspects, a method for constructing a well screen assembly includes
positioning a crimp ring encircling and over an end of a wrapped-on-pipe screen layer on
a tubular base pipe. The crimp ring is plastically deformed about an outer surface of the
screen layer. Weld is applied to affix the crimp ring to the base pipe.
[0007] In certain aspects, a method includes wrapping a wire helically around a base pipe
to define a screen layer. A crimp ring is introduced over an end of the screen layer. The
crimp ring is plastically deformed around the screen layer and securing the screen layer to
the base pipe.
[0008] One or more of the aspects include some, none or all of the following features. In
certain instances, an end ring is affixed to the base pipe and encircles the base pipe. The
crimp ring is plastically deformed about an outer surface of the end ring. The crimp ring
is welded to the end ring, and the end ring is welded to the base pipe. The end ring is
continuous or split. In certain instances, the split end ring includes a plurality of arcuate
ring segments assembled about the base pipe. In certain instances, the end ring is omitted
and the crimp ring is welded to the base pipe. The crimp ring is deformed into contact
with the outer surface of the screen layer. In certain instances, the material of the screen
layer and the material of the base pipe are incompatible for welding. In certain instances,
a second crimp ring is affixed to the base pipe and encircles the base pipe and a second
end of the screen layer, the second crimp ring plastically deformed about the outer
surface of the screen layer.
[0009] The details of one or more implementations are set forth in the accompanying
drawings and the description below. Other features, objects, and advantages will be
apparent from the description and drawings, and from the claims.
DESCRIPTION OF DRAWINGS
[0010] FIG. 1 is a side cross-sectional view of an example well system including a
plurality of well screen assemblies constructed in accordance with the concepts described
herein.
[001 1] FIGS. 2A-2C are half side cross-sectional views of a well screen assembly
constructed in accordance with the concepts described herein, wherein FIG. 2A illustrates
the completed well screen assembly, FIG. 2B illustrates the well screen assembly prior to
crimping, and FIG. 2C illustrates the well screen assembly after crimping.
[0012] FIG. 3A is a perspective view of an end ring constructed in accordance with the
concepts described herein.
[0013] FIG. 3B is a perspective view of a crimp ring constructed in accordance with the
concepts described herein.
[0014] FIGS. 4A-4C are half side cross-sectional views of another well screen assembly
constructed in accordance with the concepts described herein, wherein FIG. 4A illustrates
the completed well screen assembly, FIG. 4B illustrates the well screen assembly prior to
crimping, and FIG. 4C illustrates the well screen assembly after crimping.
[0015] Like reference symbols in the various drawings indicate like elements.
DETAILED DESCRIPTION
[0016] FIG. 1 illustrates an example well system 10 including a plurality of well screen
assemblies 12. The well system 10 is shown as being a horizontal well, having a
wellbore 14 that deviates to horizontal or substantially horizontal in the subterranean
zone of interest 24. A casing 16 is cemented in the vertical portion of the wellbore and
coupled to a wellhead 18 at the surface 20. The remainder of the wellbore 14 is
completed open hole (i.e., without casing). A production string 22 extends from wellhead
18, through the wellbore 14 and into the subterranean zone of interest 24. A production
packer 28 seals the annulus between the production string 22 and the casing 16. The
production string 22 operates in producing fluids (e.g., oil, gas, and/or other fluids) from
the subterranean zone 24 to the surface 20. The production string 22 includes one or
more well screen assemblies 12 (two shown). In some instances, the annulus between the
production string 22 and the open hole portion of the wellbore 14 may be packed with
gravel and/or sand (hereinafter referred to as gravel packing 26 for convenience). The
well screen assemblies 12 and gravel packing 26 allow communication of fluids between
the production string 22 and subterranean zone 24. The gravel packing 26 provides a first
stage of filtration against passage of particulate and larger fragments of the formation to
the production string 22. The well screen assemblies provide a second stage of filtration,
and are configured to filter against passage of particulate of a specified size and larger
into the production string 22.
[0017] Although shown in the context of a horizontal well system 10, well screen
assemblies 12 can be provided in other well configurations, including vertical well
systems having a vertical or substantial vertical wellbore, multi-lateral well systems
having multiple wellbores deviating from a common wellbore and/or other well systems.
Also, although described in a production context, well screen assemblies 12 can be used
in other contexts, including injection, well treatment and/or other applications.
[0018] FIGS. 2A-2C are half side cross-sectional views of a well screen assembly 200
constructed in accordance with the concepts described herein. The well screen assembly
200 includes an elongate tubular base pipe 210 that carries a wrapped-on-pipe screen
layer 220. The base pipe has a plurality of apertures 212 between the interior and exterior
of the base pipe to allow communication of fluid between the interior and the exterior. In
certain instances, the ends of the base pipe 210 are adapted to couple to other tubulars of
a well string (e.g., by box and pin and/or otherwise). The wrapped-on-pipe screen layer
220 is a type of screen formed by wrapping a wire 214 helically around the exterior of the
base pipe 210. In certain instances, an axial rib 215 is provided between the screen layer
220 and the base pipe 210 when the wire 214 is wrapped around the exterior of the base
pipe 210. The wire 214 can be welded to the rib 215 as it is wrapped. The screen layer
220 functions to filter against passage of particulate of a specified size and larger into the
interior of the base pipe 210. Thus, in certain instances, the pitch of the helix is selected
such that the space between adjacent turns of wire 214 at the location where the wire 214
turns are closest together is at least smaller than the specified size of the particulate. In
certain instances, the screen layer 220 can filter against passage of gravel and/or sand
sized particulate. The wire 214 can take the form of a number of different shapes. For
example, in FIG. 2A, the wire 214 is trapezoidal in axial cross-section, having a larger
transverse dimension at the outer surface of the screen layer 220 than at the inner surface
of the screen layer 220. In other instances, the wire 214 can have other different shapes,
including triangular, circular, elliptical, square, and other shapes.
[0019] The screen assembly 200 is formed by wrapping the wire 214 helically around the
exterior of the base pipe 210. Then, a end ring 216 is placed on the base pipe 210,
encircling the base pipe 210 and adjacent, and in some instances adjacent and contacting,
the end of the screen layer 220. In certain instances, the end ring 216 can be a continuous
ring. In certain instances the end ring 216 can be split such that the end ring can be
opened and placed laterally over the base pipe 210, rather than requiring the end ring to
be introduced over the end of the base pipe 210 and passed over the base pipe 210 into
position. In certain instances, the end ring 216, when split, need not account for
irregularities (e.g., ovality, thickness and diameter variations, and other irregularities)
over the entire or other length of the base pipe 210, because it need not pass over the
length of the base pipe 210. Furthermore, in certain instances, it can be more convenient
to place the end ring 216 laterally over the base pipe 210 when, for example, the screen
layer 220 terminates intermediate a length of the base pipe 210 rather than adjacent an
end.
[0020] The split end ring 216 can be two or more arcuate, C-shaped ring segments 216a,
216b as in FIG. 3A that are assembled around the base pipe 210. In other instances, the
end ring 216 can be a substantially complete ring with a single cut to allow the end ring
216 to be opened and the base pipe 210 received through the cut. A notch or partial cut
can be provided opposite the single cut to facilitate opening the end ring 216. Other
configurations are likewise possible. In certain instances, the outer diameter of the end
ring 216, when assembled around the base pipe 210, is equal to or slightly smaller than
the outer diameter of the screen layer 220. The inner diameter of the split ring 216 is
equal to or slightly larger than the outer diameter of the base pipe 210. The inner
diameter of the split ring 216 can be a loose fit over the base pipe 210 to accommodate
variations in the base pipe 210 outer diameter, ovality, and/or other irregularities of the
base pipe 210.
[0021] The end ring 216 is secured to the base pipe and/or the screen layer 220. In
certain instances, the end ring 216 is tack welded to the base pipe 210 and/or the screen
layer 220. Tack welding is a technique where short segments or points of weld are
applied at spaced out intervals, rather than a continuous or a long stitch weld. In other
instances, the end ring 216 can be clamped, secured by fasteners, secured with adhesive,
and/or secured another manner. The end ring 216 need not be permanently and strongly
secured to the base pipe 210, because as is discussed below, the end ring 216 will be
further secured to the base pipe in a later construction step. In certain instances, the end
ring 216 is provided with a weld bevel 217 opposite the surface facing the screen layer
220 to facilitate formation of a weld bead between the end ring 216 and the outer surface
of the base pipe 210.
[0022] A crimp ring 218 (FIG. 3B) is positioned encircling and over the interface
between the end ring 216 and the screen layer 220, such that a portion of the crimp ring
218 resides over the end of the screen layer 220 and a portion of the crimp ring 218
resides over the end ring 216. In certain instances, the crimp ring 218 can overlap the
screen layer 220 by 1-2 inches or more. In certain instances, the crimp ring 218 can
overlap the screen layer 220 by less. The crimp ring 218 can be a loose fit over the base
pipe 210 to accommodate variations in the screen layer 220 outer diameter, ovality,
and/or other irregularities of the screen layer 220, and allow the crimp ring 218 to be
received over the end of the screen layer 220 and moved over the screen layer into
location. Once in position, the crimp ring 218 is crimped, i.e., plastically deformed, into
close relationship and/or contact with the outer surface of the screen layer 220 and the
split ring 216 (compare FIGS. 2B and 2C). In certain instances, to prevent passage of the
specified size particulate, it is desirable to crimp the crimp ring 218 into continuous
contact around the entire circumference of the screen layer 220. In certain instances, to
prevent passage of the specified size particulate, all or a portion of the crimp ring 218 can
be crimped to close, but spaced apart proximity to the screen layer 220 with a largest
radial gap between the crimp ring 218 and screen layer 220 being at least smaller than the
specified size of particulate filtered by the screen layer 220.
[0023] Thereafter, the crimp ring 218, end ring 216 and base pipe 210 are welded
together by forming one or more beads of weld 222 circumferentially around and
contacting the interface between the crimp ring 218 and the end ring 216 and the
interface between the end ring 216 and the base pipe 210 as shown in FIG. 2A. The
beads of weld 222 can be deposited by welding, brazing, soldering, as polymer epoxy
and/or other means. Welding is joining the materials by coalescing the materials and/or a
filler material. Brazing and soldering, in the context of metallic components, are joining
the metals without coalescing the materials. The beads of weld 222 can be continuous
and seal against passage of the specified size of particulate and/or fluid between the
crimp ring 218 and end ring 216 interface and between the end ring 216 and base pipe
210, and secures the end ring 216, crimp ring 218 and screen layer 220 to the base pipe
210. In certain instances, an O-ring can additionally or alternately be provided between
crimp ring 28 and end ring 216 and/or the base pipe 210 and the end ring 216 to seal
against passage of the specified size of particulate and/or fluid. A similar or identical
assembly of crimp ring 218 and end ring 216 can be installed on opposing ends of the
screen layer 220. The crimp rings 218 and end rings 216 then bracket the screen layer
220 and retain the screen layer 220 from axially moving on the base pipe 210, as well as
prevent specified size particulate from passing between the base pipe 210 and screen
layer 220 at the ends of the screen layer 220.
[0024] Because the base pipe 210 and crimp ring 218 need not be welded to the screen
layer 220, the screen layer 220 can be made of materials that cannot be welded or readily
welded with the materials of the base pipe 210 and crimp ring 218.
[0025] FIGS. 4A-4C are half side cross-sectional views of another well screen assembly
400 constructed in accordance with the concepts described herein. As with the well
screen assembly 200 described above, the well screen assembly 400 includes a base pipe
210, a screen layer 220 formed of wire 214 helically wrapped around the base pipe 210,
and a crimp ring 218. However, the end ring 216 is omitted and the crimp ring 218 is
configured with enough material that it can be crimped both to the outer surface of the
screen layer 220 and to the outer surface of the base pipe 210. Thereafter, the crimp ring
218 is welded to the base pipe 210 by forming beads of weld circumferentially around
and contacting the interface between the crimp ring 218 and the base pipe 210.
[0026] A number of implementations have been described. Nevertheless, it will be
understood that various modifications may be made without departing from the spirit and
scope of the invention. Accordingly, other implementations are within the scope of the
following claims.

We claim:
1. A well screen assembly, comprising:
an elongate tubular base pipe defining apertures extending between the interior
and exterior of the base pipe;
a screen layer carried on the base pipe and comprising a wire that has been
wrapped helically around the exterior of the base pipe; and
a crimp ring affixed to the base pipe and encircling the base pipe and an end of
the screen layer, the crimp ring plastically deformed about an outer surface of the
screen layer.
2. The well screen assembly of claim 1, further comprising an end ring
affixed to the base pipe and encircling the base pipe, the crimp ring plastically
deformed about an outer surface of the end ring.
3. The well screen assembly of claim 2, wherein the crimp ring is welded
to the end ring, and the end ring is welded to the base pipe.
4. The well screen assembly of claim 2, wherein the end ring is split.
5. The well screen assembly of claim 4, wherein the end ring comprises a
plurality of arcuate ring segments assembled about the base pipe.
6. The well screen assembly of claim 1, wherein the crimp ring is welded
to the base pipe.
7. The well screen assembly of claim 1, wherein the crimp ring is
deformed into contact with the outer surface of the screen layer.
8. The well screen assembly of claim 1, wherein the material of the
screen layer and the material of the base pipe are incompatible for welding.
9. The well screen assembly of claim 1, further comprising a second
crimp ring affixed to the base pipe and encircling the base pipe and a second end
10
of the screen layer, the second crimp ring plastically deformed about the outer
surface of the screen layer.
10. A method for constructing a well screen, comprising:
positioning a crimp ring encircling and over an end of a wrapped-on-pipe
screen layer on a tubular base pipe;
plastically deforming the crimp ring about an outer surface of the screen layer;
and
applying a bead of weld to affix the crimp ring to the base pipe.
11. The method of claim 10, further comprising positioning an end ring
encircling the base pipe and adjacent the screen layer and plastically deforming
the crimp ring about an outer surface of the end ring.
12. The method of claim 11, wherein applying beads of weld to affix the
crimp ring to the base pipe comprises welding the crimp ring to the end ring, and
welding the end ring to the base pipe.
13. The method of claim 11, wherein the end ring is split and positing the
end ring encircling the base pipe comprises passing end ring laterally over the
base pipe.
14. The method of claim 11, wherein the end ring comprises a plurality of
arcuate ring segments, and positioning the end ring encircling the base pipe
comprises assembling the end ring segments around the base pipe.
15. The method of claim 10, wherein plastically deforming the crimp ring
about an outer surface of the screen layer comprises plastically deforming the
crimp ring into contact with the outer surface of the screen layer.
11
16. The method of claim 10, further comprising:
positioning a second crimp ring encircling and over a second end of the screen
layer;
plastically deforming the second crimp ring about the outer surface of the
screen layer; and
applying a bead of weld to affix the second crimp ring to the base pipe.
17. A method, comprising:
wrapping a wire helically around a base pipe to define a screen layer;
introducing a crimp ring over an end of the screen layer; and
plastically deforming the crimp ring around the screen layer and securing the
screen layer to the base pipe.
18. The method of claim 17, further comprising:
introducing an end ring laterally over the base pipe adjacent the end of the
screen layer; and
plastically deforming the crimp ring around the end ring
19. The method of claim 18, further comprising welding the end ring to the
base pipe and welding the crimp ring to the end ring.
20. The method of claim 17, further comprising welding the crimp ring to
the base pipe.

Documents

Application Documents

# Name Date
1 1612-DELNP-2013.pdf 2013-02-26
2 1612-delnp-2013-Form-18-(04-04-2013).pdf 2013-04-04
3 1612-delnp-2013-Correspondence Others-(04-04-2013).pdf 2013-04-04
4 1612-delnp-2013-1-GPA-(04-04-2013).pdf 2013-04-04
5 1612-delnp-2013-1-Correspondence Others-(04-04-2013).pdf 2013-04-04
6 1612-delnp-2013-Form-3-(07-06-2013).pdf 2013-06-07
7 1612-delnp-2013-Correspondence-Others-(07-06-2013).pdf 2013-06-07
8 1612-delnp-2013-Form-5.pdf 2013-08-20
9 1612-delnp-2013-Form-3.pdf 2013-08-20
10 1612-delnp-2013-Form-2.pdf 2013-08-20
11 1612-delnp-2013-Form-1.pdf 2013-08-20
12 1612-delnp-2013-Correspondence-others.pdf 2013-08-20
13 1612-delnp-2013-Claims.pdf 2013-08-20
14 Other Document [16-06-2016(online)].pdf 2016-06-16
15 Marked Copy [16-06-2016(online)].pdf 2016-06-16
16 Form 13 [16-06-2016(online)].pdf 2016-06-16
17 Description(Complete) [16-06-2016(online)].pdf 2016-06-16
18 1612-DELNP-2013-FORM-26 [28-09-2017(online)].pdf 2017-09-28
19 1612-DELNP-2013-Power of Attorney-061017.pdf 2017-10-16
20 1612-DELNP-2013-Correspondence-061017.pdf 2017-10-16
21 1612-DELNP-2013-FER.pdf 2018-06-14
22 1612-DELNP-2013-Certified Copy of Priority Document (MANDATORY) [20-07-2018(online)].pdf 2018-07-20
23 1612-DELNP-2013-OTHERS [14-11-2018(online)].pdf 2018-11-14
24 1612-DELNP-2013-Information under section 8(2) (MANDATORY) [14-11-2018(online)].pdf 2018-11-14
25 1612-DELNP-2013-FORM-26 [14-11-2018(online)].pdf 2018-11-14
26 1612-DELNP-2013-FORM 3 [14-11-2018(online)].pdf 2018-11-14
27 1612-DELNP-2013-FER_SER_REPLY [14-11-2018(online)].pdf 2018-11-14
28 1612-DELNP-2013-DRAWING [14-11-2018(online)].pdf 2018-11-14
29 1612-DELNP-2013-CORRESPONDENCE [14-11-2018(online)].pdf 2018-11-14
30 1612-DELNP-2013-COMPLETE SPECIFICATION [14-11-2018(online)].pdf 2018-11-14
31 1612-DELNP-2013-CLAIMS [14-11-2018(online)].pdf 2018-11-14
32 1612-DELNP-2013-ABSTRACT [14-11-2018(online)].pdf 2018-11-14
33 1612-DELNP-2013-RELEVANT DOCUMENTS [16-11-2018(online)].pdf 2018-11-16
34 1612-DELNP-2013-PETITION UNDER RULE 137 [16-11-2018(online)].pdf 2018-11-16
35 1612-DELNP-2013-Power of Attorney-221118.pdf 2018-11-29
36 1612-DELNP-2013-Correspondence-221118.pdf 2018-11-29
37 1612-DELNP-2013-REQUEST FOR CERTIFIED COPY [04-02-2019(online)].pdf 2019-02-04
38 1612-DELNP-2013-US(14)-HearingNotice-(HearingDate-30-07-2020).pdf 2020-07-07
39 1612-DELNP-2013-US(14)-ExtendedHearingNotice-(HearingDate-04-08-2020).pdf 2020-07-10
40 1612-DELNP-2013-RELEVANT DOCUMENTS [17-08-2020(online)].pdf 2020-08-17
41 1612-DELNP-2013-MARKED COPIES OF AMENDEMENTS [17-08-2020(online)].pdf 2020-08-17
42 1612-DELNP-2013-FORM 13 [17-08-2020(online)].pdf 2020-08-17
43 1612-DELNP-2013-AMMENDED DOCUMENTS [17-08-2020(online)].pdf 2020-08-17
44 1612-DELNP-2013-Written submissions and relevant documents [18-08-2020(online)].pdf 2020-08-18
45 1612-DELNP-2013-Annexure [18-08-2020(online)].pdf 2020-08-18
46 1612-DELNP-2013-FORM 3 [28-08-2020(online)].pdf 2020-08-28
47 1612-DELNP-2013-PatentCertificate23-10-2020.pdf 2020-10-23
48 1612-DELNP-2013-IntimationOfGrant23-10-2020.pdf 2020-10-23
49 1612-DELNP-2013-RELEVANT DOCUMENTS [13-05-2022(online)].pdf 2022-05-13
50 1612-DELNP-2013-RELEVANT DOCUMENTS [24-05-2023(online)].pdf 2023-05-24
51 1612-DELNP-2013-FORM-27 [14-08-2024(online)].pdf 2024-08-14

Search Strategy

1 1612-DELNP-2013WALLSCREENASSEMBLY_26-10-2017.pdf

ERegister / Renewals

3rd: 02 Nov 2020

From 05/08/2013 - To 05/08/2014

4th: 02 Nov 2020

From 05/08/2014 - To 05/08/2015

5th: 02 Nov 2020

From 05/08/2015 - To 05/08/2016

6th: 02 Nov 2020

From 05/08/2016 - To 05/08/2017

7th: 02 Nov 2020

From 05/08/2017 - To 05/08/2018

8th: 02 Nov 2020

From 05/08/2018 - To 05/08/2019

9th: 02 Nov 2020

From 05/08/2019 - To 05/08/2020

10th: 02 Nov 2020

From 05/08/2020 - To 05/08/2021

11th: 29 Jul 2021

From 05/08/2021 - To 05/08/2022

12th: 02 Aug 2022

From 05/08/2022 - To 05/08/2023

13th: 28 Jul 2023

From 05/08/2023 - To 05/08/2024

14th: 31 Jul 2024

From 05/08/2024 - To 05/08/2025

15th: 31 Jul 2025

From 05/08/2025 - To 05/08/2026