Abstract: The ASPHALT HOT TYPE DRUM MIX PLANT is consists With tour unit (i) Four-bin unit, (ii) Dryer unit, (iii) Asphalt tank & LDO lank (iv) filler unit. The plant relates to the apparatus and method for making asphalt- paving material. The plant having mineral aggregate supplying and heating a mixer for receiving the heated mineral aggregate and binder. The whole unit is situated at fix place. The mix material consists cold aggregate material with different size, asphalt material (liquid form) and lime/dust/cement. Cold aggregate martial with different size is loaded in the four-bin hopper then the bottom level of the four-bin hopper is connected with dryer unit with help of cold conveyor. The cold material is heated up to the half-length of the drum then the aslant material and lime/dust/ cement is mixed into the heated material. The hot mix material is then loaded on the output hopper.

Get Free WhatsApp Updates!
Notices, Deadlines & Correspondence

Patent Information

Application #
Filing Date
09 July 2004
Publication Number
0
Publication Type
INA
Invention Field
MECHANICAL ENGINEERING
Status
Email
Parent Application
Patent Number
Legal Status
Grant Date
2007-10-16
Renewal Date

Applicants

SOLID INDIA LIMITED
PLOT NO.:625, PHASE-IV, GIDC, VATVA, B/H.CIPET, AHMEDABAD

Inventors

1. DODIA NIPULBHAI HASMUKHBHAI
74, GIRIVAR BUNGALOWS, NR. RAMWADI BUS STOP, ISANPUR AHMEDABAD-382443.

Specification

FORM - 2
THE PATENTS ACT, 1970
(39 of 1970) COMPLETE SPECIFICATION
(See section 10; rule 13)
1. "HOT ASPHALT DRUM MIX PLANT"
2. (1) (a) M/S. SOLID & CORRECT ENGINEERING WORKS, , a
registered partnership firm at
(b) PLOT NO.:625, PHASE-IV, GIDC, VATVA, B/H. CIPET, AHMEDABAD-382445. GUJARAT, INDIA.
(c) INDIAN FIRM
The following specification particularly describes the nature of the invention and the manner in which it is to be performed.


The present invention relates to HOT ASPHALT DRUM MIX PLANT, the
plant relates to the apparatus and methods of producing hot asphalt mix paving material. The asphalt mixing plant for making asphalt paving mix-having mineral aggregate supplying and heating a mixer for receiving the heated mineral aggregate and binder supplying means including heating for introducing heated binder such as bitumen into the mixer.

In accordance with current environmental protection efforts, demands are made on the highway construction and repair industry to use equipment, which complies with environmental requirements. At the same time the equipment needs to produces quality highway paving materials in an efficient manner. The mixing of the constituent martial typically takes place at elevated temperatures. In the convention process asphalt materials are produced in both continuous drying
processes and in batch processes. In continuous mixing processes, co material with different sizes is dumped in the four high-rise hopers. are rise at high position so; it requires more time and consumes more fuel to Load it. Also the dryer unit is rise at high position. The dryer unit is consist with drum which rotate about axes, disposed typically at a slight incline from the horizontal and which are typically equipped with an open flame burner and a blower at one end. The long length drum creates vibrations in it so, breakdown is occurred in it and it requires more maintains in it. The inside surface of such drum:; are further equipped with spaced sets of flight which lift the material and dump i: in a falling curtain of the particulate material which exposes it to the hot gases emanating from the burner. The asphalt tank has slow heating coil system but it's temperature is very low so; it consume high fuel to heat the asphalt material and taking more time to heat the paving material. To overcome such difficulty hot asphalt drum mix plant is invented with unique design.
2

The present invention is described with great specific and clarity with reference to following drawings:
Fig. 1 represents the elevation view of the four-bin plant. Fig.2 represents the elevation view of the dryer unit Fig.3 represents the elevation view of the asphalt tank. Fig.4 represent the elevation view of the filler unit.
The hot asphalt drum mix plant consists four units (i) four-bin unit, (ii) dryer unit, (iii) asphalt tank and (iv) filler unit. Four-bin unit is represents in Fig.l consists chassis (1), hopper (2), door (3), hopper belt (4), gathering belt (5) wherein cold aggregate materials with different size (as per requires) is dumped in low-rise hopper (2). Cold aggregate materials flow from door (3) of all bins with different size material with variable speed, which is controlled by the doors provided at the downside of the all bins. Total aggregate materials will dump on gathering belt (5) and it is fitted on bottom level of cold aggregate bin feeder. The gathering conveyor belt (5) is moves with total flow through and screened by vibratory screening (6) for over sized materials. Then total and actual materials will go to cold conveyor belt (7) as shown in Fig.2. The cold conveyor belt (7) is mounted on the cold conveyor (8). Now the cold conveyor belt (7) system dumped with total flow in the rotating drum (9) for aggregate heating process. In dryer unit motor rotates drum (9) with fuel burner (10) and aggregate will heated as per requirement and the mix materials reach up to half length of the rotating drum (9). Guide roller (11) and two-support rollers (12) are mounted on chassis (13) of dryer 'unit to provide batter support and vibration free motion to the rotating drum (9). The rotating drum (9) is also guide by- the guide ring (14). Sprocket ring (15) is mounted on the chassis (13) to provide better support to the drum (9). Chamber (16) is connected with drum (9) of the dryer unit. Exhaust (18) and chimney (19)
3

)

are connected with dust collector (17). At the same time asphalt tank (25) as shown in Fig.3 heat the, asphalt (bitumen). The asphalt tank is fitted with a fuel burner (10) for heating of asphalt (bitumen) and then the heated asphalt materials (liquid foam) is spared as per the requirements it will go in to the rotating drum (9). Asphalt tank (25) and LDO (Low diesel oil) tank (26) unit is mounted on the chassis (29). Heating coil (20) is providing better heating surface to heatj the asphalt (bitumen) material inside the rotating drum (9). Exhaust Fan exhaust fine dust of aggregate and burner smoker to the chimney (19). Tank door (33) is position at the top of the asphalt tank (25) to clean it. Filler unit is separately shown in Fig.4 consists with hopper (30), rotary valve (31), butter fry valve (32) and 'T' connection (34) wherein whole unit is mounted near the dryer unit. It is working for storage of lime/dust/cement filler line and spraying on heated aggregate in the drum (9) up to the process of mix materials. Then the mix material will come at the down stage of the hot conveyor belt (21) due to the gravitational force thought the door which was provided on the rotating drum. Then the mix material was loaded on the output hopper (22). The hot conveyor belt (21) is mounted on the hot conveyor (23). When the hot mix asphalt paving material is stored in the output hopper (22) then the dumper is take under this output hopper (22) and output hopper (22) is opens with the help of hopper jack (24). The fully loaded dumper of heated mix materials carry where the required of road laying.

4

We Claims:
I. HOT ASPHALT DRUM MIX PLANT consists four units (i) Four-bin
unit, (ii) Dryer unit, (iii) Asphalt tank & LDO (light diesel oil) tank and (iv)
filler unit wherein
(a) hopper(2) of four-bins unit is mounted on chassis (1) where the door (3) is positioned below the hopper(2) then hopper belt (4) & gathering belt (5) are sequentially fitted below the door(3);
(b) dryer unit consists vibrating screen (6) which is situated on cold conveyor belt(7) fitted on cold conveyor (8) to deliver cold aggregate materials with different size into the rotating drum (9) which is guide by guide: roller (l 1), support roller (12) and guide ring (14) & sprocket ring (15) is position at the half length of the rotating drum (9) which is mounted on the chassis (13) and burner (10) fitted inside the rotating drum(9) at the near end of jcold conveyer belt(7) and chamber (16) is situated at the other end of rotating drum (9) where exhaust (18) & chimney (19) are connected with dust collector (17) then the hot mix asphalt material comes on hot conveyor belt (21) fitted on hot conveyor(23) then the hot mix materials deliver into the output hopper (22) where hopper jack (24) is connected with output hopper (22);
(c) in asphalt tank unit burner (10) is fitted inside the rotating druijn at the near end of the cold conveyer belt to heat the asphalt material and the heating
coil (20) is positioned inside the rotating drum (9) then asphalt tank (25) &
i
LDO Light diesel oil) tank (26) is positioned at the both side of the rotating
5

drum (9) and the other mounting i.e. out let valve (27), drain valve (28) and tank door(33) are mounted on chassis(29);
(d) filler unit consists hopper (30), rotary valve(31), butter fly valve(32) and T' connection (34) wherein whole unit is mounted near the dryer unlit

sequence wise
HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 wherein doors (3), hopper belts (4) & gathering belt (5) are mounted from the output of each hopper (2).

3. HOT ASPHALT DRUM MIX PLANT as claimed in clairii 1 wherein rotating drum (9) is slight inclined from the horizontal axis wherein burner (10) is positioned at high position from the horizontal axis.

4. HOT ASPHALT DRUM MIX PLANT as claimed in claim guide roller (11), support rollers (12), guide ring (14) and sprocket are mounted on the chassis (13).
1 wherein
j
ring (15)
J
5. HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 wherein
cold conveyor belt (7) is attached between the output of the bin feeder and
rotating drum (9).
6. HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 wherein hot conveyor belt (21) is attached between the output of the drum feeder and output hopper (22).
6

7. HOT ASPHALT DRUM MIX PLANT as claimed in claim wherein hopper jack (24) is mounted on the output hopper (22).
8. HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 wherein chamber (16) is connected with rotating drum (9) of the dryer unit

9. HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 heating coil (20 is mounted inside the asphalt tank (25) & LDO tank unit (26).

10 HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 wherein tank door (33) is positioned at the top of the asphalt tank (25).
11. HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 wherein drain valve (28) is mounted below the asphalt tank (25).
12. HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 wherein filler unit is mounted near the dryer unit.
13. HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 wherein butter fly valve (32) is connected with the output of hopper (30).
14. HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 wherein rotary valve (31) joints the butter fly valve (32) and T' connection (34).
7

15. HOT ASPHALT DRUM MIX PLANT as claimed in claim 1 wherein substantially herein described with reference to the foregoing description and the accompanying drawings.
Dated this on 2nd July, 2004.

8
Abstract
The ASPHALT HOT TYPE DRUM MIX PLANT is consists With tour
unit (i) Four-bin unit, (ii) Dryer unit, (iii) Asphalt tank & LDO lank (iv)
filler unit. The plant relates to the apparatus and method for making asphalt-
paving material. The plant having mineral aggregate supplying and heating a
mixer for receiving the heated mineral aggregate and binder. The whole unit
is situated at fix place. The mix material consists cold aggregate material
with different size, asphalt material (liquid form) and lime/dust/cement. Cold
aggregate martial with different size is loaded in the four-bin hopper then the
bottom level of the four-bin hopper is connected with dryer unit with help of
cold conveyor. The cold material is heated up to the half-length of the drum
then the aslant material and lime/dust/ cement is mixed into the heated
material. The hot mix material is then loaded on the output hopper.

Documents

Application Documents

# Name Date
1 210970-FORM 27-2013.pdf 2024-03-02
1 733-mum-2004-form 5(09-07-2004).pdf 2004-07-09
2 733-mum-2004-form 3(09-07-2004).pdf 2004-07-09
2 733-mum-2004-abstract.doc 2018-08-09
3 733-mum-2004-form 1(09-07-2004).pdf 2004-07-09
3 733-mum-2004-abstract.pdf 2018-08-09
4 733-mum-2004-form 19(03-08-2004).pdf 2004-08-03
5 733-mum-2004-form 2(granted)-(03-12-2004).pdf 2004-12-03
5 733-mum-2004-claims.pdf 2018-08-09
6 733-mum-2004-correspondence-received-021204.pdf 2018-08-09
7 733-mum-2004-correspondence-received-080704.pdf 2018-08-09
7 733-mum-2004-claims(granted)-(03-12-2004).pdf 2004-12-03
8 733-mum-2004-correspondence-received-280704.pdf 2018-08-09
9 733-mum-2004-correspondence-received.pdf 2018-08-09
9 733-mum-2004-cancelled pages(03-12-2004).pdf 2004-12-03
10 733-mum-2004-correspondence(ipo)-(12-08-2005).pdf 2005-08-12
10 733-mum-2004-description (complete).pdf 2018-08-09
11 733-mum-2004-drawing(24-10-2005).pdf 2005-10-24
11 733-mum-2004-drawings.pdf 2018-08-09
12 733-mum-2004-declaration(24-10-2005).pdf 2005-10-24
12 733-mum-2004-form-1.pdf 2018-08-09
13 733-mum-2004-form-19.pdf 2018-08-09
14 733-mum-2004-form 26(09-07-2007).pdf 2007-07-09
15 733-mum-2004-assignment of invention(03-09-2007).pdf 2007-09-03
15 733-mum-2004-form-2.pdf 2018-08-09
16 733-mum-2004-form-26.pdf 2018-08-09
16 733-mum-2004-form 26(10-09-2007).pdf 2007-09-10
17 733-mum-2004-form-3.pdf 2018-08-09
17 733-mum-2004-correspondence(10-09-2007).pdf 2007-09-10
18 733-mum-2004-form 6(13-09-2007).pdf 2007-09-13
18 733-mum-2004-form-5.pdf 2018-08-09
19 abstract1.jpg 2018-08-09
20 733-mum-2004-form 6(13-09-2007).pdf 2007-09-13
20 733-mum-2004-form-5.pdf 2018-08-09
21 733-mum-2004-correspondence(10-09-2007).pdf 2007-09-10
21 733-mum-2004-form-3.pdf 2018-08-09
22 733-mum-2004-form 26(10-09-2007).pdf 2007-09-10
22 733-mum-2004-form-26.pdf 2018-08-09
23 733-mum-2004-assignment of invention(03-09-2007).pdf 2007-09-03
23 733-mum-2004-form-2.pdf 2018-08-09
24 733-mum-2004-form 26(09-07-2007).pdf 2007-07-09
25 733-mum-2004-form-19.pdf 2018-08-09
26 733-mum-2004-declaration(24-10-2005).pdf 2005-10-24
26 733-mum-2004-form-1.pdf 2018-08-09
27 733-mum-2004-drawing(24-10-2005).pdf 2005-10-24
27 733-mum-2004-drawings.pdf 2018-08-09
28 733-mum-2004-description (complete).pdf 2018-08-09
28 733-mum-2004-correspondence(ipo)-(12-08-2005).pdf 2005-08-12
29 733-mum-2004-cancelled pages(03-12-2004).pdf 2004-12-03
29 733-mum-2004-correspondence-received.pdf 2018-08-09
30 733-mum-2004-correspondence-received-280704.pdf 2018-08-09
31 733-mum-2004-correspondence-received-080704.pdf 2018-08-09
31 733-mum-2004-claims(granted)-(03-12-2004).pdf 2004-12-03
32 733-mum-2004-correspondence-received-021204.pdf 2018-08-09
33 733-mum-2004-form 2(granted)-(03-12-2004).pdf 2004-12-03
33 733-mum-2004-claims.pdf 2018-08-09
34 733-mum-2004-form 19(03-08-2004).pdf 2004-08-03
35 733-mum-2004-abstract.pdf 2018-08-09
35 733-mum-2004-form 1(09-07-2004).pdf 2004-07-09
36 733-mum-2004-form 3(09-07-2004).pdf 2004-07-09
37 210970-FORM 27-2013.pdf 2024-03-02
37 733-mum-2004-form 5(09-07-2004).pdf 2004-07-09

ERegister / Renewals

3rd: 18 Feb 2008

From 09/07/2006 - To 09/07/2007

4th: 18 Feb 2008

From 09/07/2007 - To 09/07/2008

5th: 18 Feb 2008

From 09/07/2008 - To 09/07/2009

6th: 18 Feb 2008

From 09/07/2009 - To 09/07/2010

7th: 26 Jul 2010

From 09/07/2010 - To 09/07/2011

8th: 26 Jul 2010

From 09/07/2011 - To 09/07/2012

9th: 26 Jul 2010

From 09/07/2012 - To 09/07/2013