Method For Preparing Piping Diagram, And Device For Preparing Piping Diagram

Abstract: This device for preparing a piping diagram: assigns a plurality of straight pipes and cut pipes between intersection points and generates virtual pipe paths specified using characteristic evaluation data represented by a sequence, using a join angle ?i of the joint parts of the straight pipes and cut pipes, and an adjustment amount Lj of the cut pipe length, as variables; calculates an evaluation value for each virtual pipe path on the basis of the differential value between the total number of intersection points and control points and a continuous number from a starting point, which is the number of intersection points and control points at which the deviation between the virtual pipe path and the intersection points and control points is less than or equal to a prescribed threshold value, the deviation at the intersection points or control points at which the threshold value is initially exceeded, the average value of the deviation at the intersection points and control points at which the difference is less than or equal to the threshold value, and the proportion, within the range from the starting point to the intersection points and control points at which the difference is less than or equal to the threshold value, of the number of joint parts for which the join angle ?i is other than 0°; and generates a pipe path joint diagram on the basis of one virtual pipe path having a superior evaluation value.

Get Free WhatsApp Updates!
Notices, Deadlines & Correspondence

Patent Information

Application #
Filing Date
23 November 2022
Publication Number
52/2022
Publication Type
INA
Invention Field
MECHANICAL ENGINEERING
Status
Email
hkpatent@hkindia.com
Parent Application

Applicants

KUBOTA CORPORATION
1-2-47, Shikitsuhigashi, Naniwa-ku, Osaka-shi, Osaka 5568601

Inventors

1. TAKAHASHI Shimpei
c/o Kubota Corporation, Tokyo Head Office, 1-3, Kyobashi 2-chome, Chuo-ku, Tokyo 1048307
2. HAYASHI Mitsuo
c/o Kubota Corporation, Tokyo Head Office, 1-3, Kyobashi 2-chome, Chuo-ku, Tokyo 1048307
3. MITSUMORI Seiki
c/o Kubota Corporation, Tokyo Head Office, 1-3, Kyobashi 2-chome, Chuo-ku, Tokyo 1048307
4. MARUYAMA Yoshihisa
5-16-702, Urashima-cho, Kanagawa-ku, Yokohama-shi, Kanagawa 2210042

Claims

1. A piping diagram creation method for creating a piping diagram of a pipeline connecting a plurality of intersections (IP) specified on a map between a start point and an end point and passing through a control point (CP) selectively specified between the respective intersections (IP), the method comprising: a first step of selecting fittings to be disposed at the respective intersections (IP); a second step of determining a number of straight pipes required, presence or absence of cut pipes, and a length of the cut pipes, based on a distance between the respective intersections (IP) and a length of the straight pipes; a third step of generating virtual pipelines on which the straight pipes and the cut pipes determined at the second step are allocated between the respective intersections (IP), each of the virtual pipelines being identified by characteristic evaluation data expressed as a sequence of numbers with an assembling angle θi (i is a number of assembling portions) of assembling portions of the respective straight pipes and cut pipes constituting the virtual pipeline and an adjustment margin Lj (j is a number of cut pipes) of the cut pipe length as variables that are settable within a predetermined allowable range; a fourth step of calculating an evaluation value of each of the virtual pipelines generated at the third step based on (1) a first characteristic value identified by a difference value between a total number of intersections (IP) and control points (CP) and a number of intersections (IP) and control points (CP) each having an error at or below a predetermined threshold, the latter number being a continuous count from the start point, the error being defined as an amount of misalignment between the virtual pipeline and 34 each intersection (IP) and between the virtual pipeline and each control point (CP), (2) a second characteristic value identified by the error at one of the intersections (IP) or the control point (CP) that first exceeds the threshold, (3) a third characteristic value identified by an average value of the errors at the intersections (IP) and the control point (CP) having the errors at or below the threshold, and (4) a fourth characteristic value identified by a proportion of a number of assembling portions with the assembling angle θi of other than 0 degrees, within a range from the start point to the intersections (IP) and the control point (CP) having the errors at or below the threshold; a fifth step of selecting one virtual pipeline from the virtual pipelines based on the evaluation value; and a sixth step of generating a pipeline assembling diagram based on characteristic evaluation data of the virtual pipeline selected at the fifth step.

2. The piping diagram creation method according to claim 1, wherein the evaluation value is a sum of products of the respective characteristic values by predetermined weighting factors for the respective characteristic values.

3. The piping diagram creation method according to claim 1 or 2, wherein the third step includes forming the respective virtual pipelines from individuals including, as genes, the assembling angle θi (i is the number of assembling portions) of the assembling portions of the respective straight pipes and cut pipes and the adjustment margin Lj (j is the number of cut pipes) of the cut pipe length, the fifth step includes executing a genetic algorithm to generate an individual 35 with optimized genes, the genetic algorithm iterating a generation change process including any of a selection process of selecting one or more certain individuals based on evaluation values of respective individuals, a crossover process of recombining genes between individuals, and a mutation process of changing genes of any individual, and the sixth step includes generating a pipeline assembling diagram based on the optimized genes of the individual.

4. The piping diagram creation method according to claim 3, wherein the selection process includes an elite strategy method of extracting an individual with a best evaluation value from all of the individuals and a tournament method of iterating a process of selecting an individual with a relatively good evaluation value from any number of individuals randomly selected from remaining ones of the individuals until a number of individuals obtained by the selection process equals a number of individuals of a relevant generation.

5. The piping diagram creation method according to claim 3 or 4, wherein the crossover process includes a process of taking adjacent even-numbered and odd-numbered ones of the individuals with a certain probability and performing crossover of genes by a two-point crossover method.

6. The piping diagram creation method according to any one of claims 3 to 5, wherein the mutation process includes a process of selecting a certain proportion of individuals with lesser evaluation values from the individuals and setting all genes 36 thereof to zero.

7. The piping diagram creation method according to any one of claims 3 to 6, wherein the mutation process includes a process of swapping any adjacent genes of an individual extracted with a certain probability from the individuals.

8. The piping diagram creation method according to any one of claims 1 to 7, further comprising a pre-determination step of determining in advance whether it is possible to carry out a piping layout along a straight line connecting respective intersections (IP), based on shapes of fittings to be disposed at the respective intersections (IP) or presence/absence of a control point (CP) specified between the respective intersections (IP), wherein upon determination at the pre-determination step that it is impossible to carry out the piping layout along the straight line connecting the intersections (IP), the second to sixth steps are performed.

9. A piping diagram creation device for creating a piping diagram of a pipeline connecting a plurality of intersections (IP) specified on a map between a start point and an end point and passing through a control point (CP) selectively specified between the respective intersections (IP), the device comprising: a first calculation section configured to select fittings to be disposed at the respective intersections (IP); a second calculation section configured to determine a number of straight pipes required, presence or absence of cut pipes, and a length of the cut pipes, based on a 37 distance between the respective intersections (IP) and a length of the straight pipes; a third calculation section configured to generate virtual pipelines on which the straight pipes and the cut pipes determined by the second calculation section are allocated between the respective intersections (IP), each of the virtual pipelines being identified by characteristic evaluation data expressed as a sequence of numbers with an assembling angle θi (i is a number of assembling portions) of assembling portions of the respective straight pipes and cut pipes constituting the virtual pipeline and an adjustment margin Lj (j is a number of cut pipes) of the cut pipe length as variables that are settable within a predetermined allowable range; a fourth calculation section configured to calculate an evaluation value of each of the virtual pipelines generated by the third calculation section based on (1) a first characteristic value identified by a difference value between a total number of intersections (IP) and control points (CP) and a number of intersections (IP) and control points (CP) each having an error at or below a predetermined threshold, the latter number being a continuous count from the start point, the error being defined as an amount of misalignment between the virtual pipeline and each intersection (IP) and between the virtual pipeline and each control point (CP), (2) a second characteristic value identified by the error at one of the intersections (IP) or the control point (CP) that first exceeds the threshold, (3) a third characteristic value identified by an average value of the errors at the intersections (IP) and the control point (CP) having the errors at or below the threshold, and (4) a fourth characteristic value identified by a proportion of a number of assembling portions with the assembling angle θi of other than 0 degrees, within a range from the start point to the intersections (IP) and the control point (CP) having the 38 errors at or below the threshold; a fifth calculation section configured to select one virtual pipeline from the virtual pipelines based on the evaluation value; a sixth calculation section configured to generate a pipeline assembling diagram based on characteristic evaluation data of the virtual pipeline selected by the fifth calculation section.

10. The piping diagram creation device according to claim 9, wherein the evaluation value is a sum of products of the respective characteristic values by predetermined weighting factors for the respective characteristic values.

11. The piping diagram creation device according to claim 9 or 10, wherein the third calculation section is configured to form the respective virtual pipelines from individuals including, as genes, the assembling angle θi (i is the number of assembling portions) of the assembling portions of the respective straight pipes and cut pipes and the adjustment margin Lj (j is the number of cut pipes) of the cut pipe length, the fifth calculation section is configured to execute a genetic algorithm to generate an individual with optimized genes, the genetic algorithm iterating a generation change process including any of a selection process of selecting one or more certain individuals based on evaluation values of respective individuals, a crossover process of recombining genes between individuals, and a mutation process of changing genes of any individual, and the sixth calculation section is configured to generate a pipeline assembling diagram based on the optimized genes of the individual. 39

12. The piping diagram creation device according to claim 11, wherein the selection process includes an elite strategy method of extracting an individual with a best evaluation value from all of the individuals and a tournament method of iterating a process of selecting an individual with a relatively good evaluation value from any number of individuals randomly selected from remaining ones of the individuals until a number of individuals obtained by the selection process equals a number of individuals of a relevant generation.

Specification

FORM 2
THE PATENTS ACT 1970
(39 of 1970)
&
The Patents Rules, 2003
COMPLETE SPECIFICATION
(See section 10 and rule 13)
1. PIPING DIAGRAM CREATION METHOD AND PIPING DIAGRAM
CREATION DEVICE
2.
1. (A) KUBOTA CORPORATION
(B) Japan
(C) 1-2-47, Shikitsuhigashi, Naniwa-ku, Osaka-shi, Osaka 5568601 JAPAN
The following specification particularly describes the invention and the manner in
which it is to be performed.

2
Technical Field
[0001] The present invention relates to a piping diagram creation method and a piping
diagram creation device.
Background Art
[0002] Patent Literature 1 discloses a drawing information management device
including: a storage means configured to store installation drawing information for a
fluid supply facility as a piping network consisting of intersection points of fluid supply
pipes and a single pipeline that is a collection of a plurality of fluid supply pipes in
series and connects the intersection points; a region identification means configured to
identify a construction region within the information stored in the storage means; and an
output means configured to output the installation drawing information for the
construction region identified by the region identification means to a plotter configured
to create construction drawings. The drawing information management device
performs a piping layout process of connecting the single pipeline between the
intersections with a plurality of straight pipes.
[0003] When a newly laid pipeline is designed or a pipeline to renew an existing one is
designed using a piping diagram creation device with an application program for
creating piping diagrams installed, a conventional method creates a planned piping route
as follows: via a pointing device, locations of fittings such as bends are specified as
intersections on a pipeline diagram layer superimposed on a map layer displayed on a
screen; and the fittings at the respective intersections are connected with a plurality of
straight pipes.
[0004] There is also a piping diagram creation device that incorporates an automatic
piping layout function to automatically perform a piping layout process, taking into
3
account the complexity for designers to perform a piping layout process of manually
selecting and laying out a pipeline along a planned piping route.
Citation List
Patent Literature
[0005] Patent Literature 1: Japanese Unexamined Patent Application Publication No.
08-287132
Summary of Invention
Technical Problem
[0006] However, as shown in Fig. 1A, in cases where a branch pipeline 2 branching
off at a predetermined intersection IP2 from a main pipeline 1 that connects
intersections IP1-IP3 in a straight line is formed and the branch pipeline 2 connecting
the branch point IP2 and an intersection IP4 on the branch route is inclined at any
inclination angle with respect to the main pipeline 1, performing a piping layout process
using the above automatic piping layout function will lead to a problem. Specifically,
as shown in Fig. 1B, a socket of a fitting DP such as a double socket tee disposed at the
branch point IP2 will be designed at an angle different from its original shape, and also
the straight pipes SP will be disposed in a straight line due to inability to bend the
straight pipes SP utilizing their permitted bending angles at pipe assembling portions.
As such, the automatic piping layout function can only generate piping diagrams in
which intersections are merely connected with a straight line.
[0007] Since it is impossible to perform the pipe laying work based on such a piping
diagram, the automatic piping layout function is indeed unusable and designers have to
perform a complicated piping layout process of manually selecting and laying out pipes
4
of fittings to be installed.
[0008] In view of the above problems, it is an object of the present invention to
provide a piping diagram creation method and a piping diagram creation device capable
of automatically generating a piping diagram that can be utilized in actual laying work
independently of angles at branch portions and other factors.
Solution to Problem
[0009] To solve the above problems, as a first feature of a piping diagram creation
method according to the present invention, the method creates a piping diagram of a
pipeline connecting a plurality of intersections (IP) specified on a map between a start
point and an end point and passing through a control point (CP) selectively specified
between the respective intersections (IP) and includes the following steps:
a first step of selecting fittings to be disposed at the respective intersections
(IP);
a second step of determining a number of straight pipes required, presence or
absence of cut pipes, and a length of the cut pipes, based on a distance between the
respective intersections (IP) and a length of the straight pipes;
a third step of generating virtual pipelines on which the straight pipes and the
cut pipes determined at the second step are allocated between the respective
intersections (IP), each of the virtual pipelines being identified by characteristic
evaluation data expressed as a sequence of numbers with an assembling angle θi (i is a
number of assembling portions) of assembling portions of the respective straight pipes
and cut pipes constituting the virtual pipeline and an adjustment margin Lj (j is the
number of cut pipes) of the cut pipe length as variables that are settable within a
predetermined allowable range;
5
a fourth step of calculating an evaluation value of each of the virtual pipelines
generated at the third step based on (1) a first characteristic value identified by a
difference value between a total number of intersections (IP) and control points (CP)
and a number of intersections (IP) and control points (CP) each having an error at or
below a predetermined threshold, the latter number being a continuous count from the
start point, the error being defined as an amount of misalignment between the virtual
pipeline and each intersection (IP) and between the virtual pipeline and each control
point (CP), (2) a second characteristic value identified by the error at one of the
intersections (IP) or the control point (CP) that first exceeds the threshold, (3) a third
characteristic value identified by an average value of the errors at the intersections (IP)
and the control point (CP) having the errors at or below the threshold, and (4) a fourth
characteristic value identified by a proportion of a number of assembling portions with
the assembling angle θi of other than 0 degrees, within a range from the start point to
the intersections (IP) and the control point (CP) having the errors at or below the
threshold; a fifth step of selecting one virtual pipeline from the virtual pipelines based
on the evaluation value; and a sixth step of generating a pipeline assembling diagram
based on characteristic evaluation data of the virtual pipeline selected at the fifth step.
[0010] At the first step, fittings to be disposed at the plurality of intersections (IP)
specified on a map between a start point and an end point are selected. At the second
step, the number of straight pipes required, the presence or absence of cut pipes, and a
length of the cut pipes are determined based on a distance between the respective
intersections (IP) and a length of the straight pipes. At the third step, virtual pipelines
are generated on which the thus determined straight and cut pipes are allocated between
the respective intersections (IP). Each of the virtual pipelines is identified by
characteristic evaluation data expressed as a sequence of numbers with the assembling
6
angle θi (i is the number of assembling portions) of assembling portions of the
respective straight pipes and cut pipes and an adjustment margin Lj (j is the number of
cut pipes) of the cut pipe length as variables that are settable within a predetermined
allowable range.
[0011] At the fourth step, the first characteristic value, the second characteristic value,
the third characteristic value, and the fourth characteristic value are calculated, and an
evaluation value for evaluating each virtual pipeline identified by the characteristic
evaluation data is calculated based on these characteristic values. The first
characteristic value is a difference value between the total number of intersections (IP)
and control points (CP) and the number of intersections (IP) and control points (CP)
each having an error at or below a predetermined threshold, the latter number being a
continuous count from the start point, the error being defined as an amount of
misalignment between the virtual pipeline and each intersection (IP) and between the
virtual pipeline and each control point (CP). The second characteristic value is the
error at one of the intersections (IP) or the control point (CP) that first exceeds the
threshold. The third characteristic value is an average value of the errors at the
intersections (IP) and the control point (CP) having the errors at or below the threshold.
The fourth characteristic value is a proportion of the number of assembling portions
with the assembling angle θi of other than 0 degrees, out of the intersections (IP) having
the errors at or below the threshold.
[0012] At the fifth step, one virtual pipeline is selected from the virtual pipelines based
on the evaluation values. At the sixth step, a pipeline assembling diagram is generated
based on the characteristic evaluation data of the virtual pipeline selected at the fifth
step.
[0013] In addition to the first feature above, the piping diagram creation method in
7
accordance with the present invention has a second feature that the evaluation value is a
sum of products of the respective characteristic values by predetermined weighting
factors for the respective characteristic values.
[0014] Each of the plurality of virtual pipelines identified by the characteristic
evaluation data is evaluated using, as the evaluation value, a sum of products of the
respective characteristic values by predetermined weighting factors for the respective
characteristic values. As such, contributions of the respective characteristic values to
the evaluation value can be adjusted by the weighting factors, resulting in a
well-balanced evaluation value.
[0015] In addition to the first or second feature above, the piping diagram creation
method in accordance with the present invention has a third feature that the third step
includes forming the respective virtual pipelines from individuals including, as genes,
the assembling angle θi (i is the number of assembling portions) of the assembling
portions of the respective straight pipes and cut pipes and the adjustment margin Lj (j is
the number of cut pipes) of the cut pipe length, the fifth step includes executing a
genetic algorithm to generate an individual with optimized genes, the genetic algorithm
iterating a generation change process including any of a selection process of selecting
one or more certain individuals based on evaluation values of respective individuals, a
crossover process of recombining genes between individuals, and a mutation process of
changing genes of any individual, and the sixth step includes generating a pipeline
assembling diagram based on the optimized genes of the individual.
[0016] Each virtual pipeline is defined as an individual including, as genes, the
assembling angle θi (i is the number of assembling portions) of the assembling portions
of the respective straight pipes and cut pipes and the adjustment margin Lj (j is the
number of cut pipes) of the cut pipe length, and an genetic algorithm is executed on the
8
virtual pipelines as a plurality of individuals having different genes, whereby an
appropriate pipeline assembling diagram is automatically generated based on genes of
an individual having undergone the generation change process. The generation change
process includes any one of or any combination of the selection process, the crossover
process, and the mutation process.
[0017] In addition to the third feature above, the piping diagram creation method in
accordance with the present invention has a fourth feature that the selection process
includes an elite strategy method of extracting an individual with a best evaluation value
from all of the individuals and a tournament method of iterating a process of selecting
an individual with a relatively good evaluation value from any number of individuals
randomly selected from remaining ones of the individuals until a number of individuals
obtained by the selection process equals a number of individuals of a relevant
generation.
[0018] The number of individuals individually identifying virtual pipelines of a certain
generation is the population. Employing the elite strategy method allows an individual
with the best evaluation value out of the virtual pipelines of the certain generation to
survive into the next generation. Also, employing the tournament method allows
individuals with more excellent genes to survive into the next generation by iterating the
process of selecting an individual with a relatively excellent evaluation value from any
number of individuals randomly selected from the certain generation until the number
of selected individuals equals the population.
[0019] In addition to the third or fourth feature above, the piping diagram creation
method in accordance with the present invention has a fifth feature that the crossover
process includes a process of taking adjacent even-numbered and odd-numbered ones of
the individuals with a certain probability and performing crossover of genes by a
9
two-point crossover method.
[0020] In the crossover process, it is preferable to take adjacent even-numbered and
odd-numbered ones of the individuals with a certain probability and perform crossover
of genes by a two-point crossover method.
[0021] In addition to any one of the third to fifth features above, the piping diagram
creation method in accordance with the present invention has a sixth feature that the
mutation process includes a process of selecting a certain proportion of individuals with
lesser evaluation values from the individuals and setting all genes thereof to zero.
[0022] Through the mutation process of setting all genes of a certain proportion of
individuals with lesser evaluation values to zero, virtual pipelines with genes exhibiting
straight pipeline shapes can survive into the next generation at a certain ratio. In the
context of generating a straight pipeline, iterating such a process can generate a pipeline
having excellent linearity with less fluctuations, rather than a straight pipeline that has
many fluctuations with repeated unnecessary bends of assembling portion of pipe.
[0023] In addition to any one of the third to sixth features above, the piping diagram
creation method in accordance with the present invention has a seventh feature that the
mutation process includes a process of swapping any adjacent genes of an individual
extracted with a certain probability from the individuals.
[0024] Swapping arbitrarily selected genes has a large effect on the entire pipeline,
which would make it difficult to improve the evaluation value even through
generational changes. However, swapping adjacent genes allows for fine adjustment
while reducing the effect on the entire pipeline.
[0025] In addition to any one of the first to seventh features above, the piping diagram
creation method in accordance with the present invention has an eighth feature that the
method further includes a pre-determination step of determining in advance whether it is
10
possible to carry out a piping layout along a straight line connecting respective
intersections (IP), based on shapes of fittings to be disposed at the respective
intersections (IP) or presence/absence of a control point (CP) specified between the
respective intersections (IP), and upon determination at the pre-determination step that it
is impossible to carry out the piping layout along the straight line connecting the
intersections (IP), the second to sixth steps are performed.
[0026] Upon determination at the pre-determination step that it is impossible to carry
out the piping layout along the straight line connecting the intersections, the second to
sixth steps are performed, which facilitates an efficient process.
[0027] As a first feature of a piping diagram creation device according to the present
invention, the device creates a piping diagram of a pipeline connecting a plurality of
intersections (IP) specified on a map between a start point and an end point and passing
through a control point (CP) selectively specified between the respective intersections
(IP) and includes: a first calculation section configured to select fittings to be disposed
at the respective intersections (IP); a second calculation section configured to determine
a number of straight pipes required, presence or absence of cut pipes, and a length of the
cut pipes, based on a distance between the respective intersections (IP) and a length of
the straight pipes; a third calculation section configured to generate virtual pipelines on
which the straight pipes and the cut pipes determined by the second calculation section
are allocated between the respective intersections (IP), each of the virtual pipelines
being identified by characteristic evaluation data expressed as a sequence of numbers
with an assembling angle θi (i is a number of assembling portions) of assembling
portions of the respective straight pipes and cut pipes constituting the virtual pipeline
and an adjustment margin Lj (j is a number of cut pipes) of the cut pipe length as
variables that are settable within a predetermined allowable range; a fourth calculation
11
section configured to calculate an evaluation value of each of the virtual pipelines
generated by the third calculation section based on (1) a first characteristic value
identified by a difference value between a total number of intersections (IP) and control
points (CP) and a number of intersections (IP) and control points (CP) each having an
error at or below a predetermined threshold, the latter number being a continuous count
from the start point, the error being defined as an amount of misalignment between the
virtual pipeline and each intersection (IP) and between the virtual pipeline and each
control point (CP), (2) a second characteristic value identified by the error at one of the
intersections (IP) or the control point (CP) that first exceeds the threshold, (3) a third
characteristic value identified by an average value of the errors at the intersections (IP)
and the control point (CP) having the errors at or below the threshold, and (4) a fourth
characteristic value identified by a proportion of a number of assembling portions with
the assembling angle θi of other than 0 degrees, within a range from the start point to
the intersections (IP) and the control point (CP) having the errors at or below the
threshold; a fifth calculation section configured to select one virtual pipeline from the
virtual pipelines based on the evaluation value; a sixth calculation section configured to
generate a pipeline assembling diagram based on characteristic evaluation data of the
virtual pipeline selected by the fifth calculation section.
[0028] In addition to the first feature above, the piping diagram creation device in
accordance with the present invention has a second feature that the evaluation value is a
sum of products of the respective characteristic values by predetermined weighting
factors for the respective characteristic values.
[0029] In addition to the first or second feature above, the piping diagram creation
device in accordance with the present invention has a third feature that the third
calculation section is configured to form the respective virtual pipelines from
12
individuals including, as genes, the assembling angle θi (i is the number of assembling
portions) of the assembling portions of the respective straight pipes and cut pipes and
the adjustment margin Lj (j is the number of cut pipes) of the cut pipe length, the fifth
calculation section is configured to execute a genetic algorithm to generate an individual
with optimized genes, the genetic algorithm iterating a generation change process
including any of a selection process of selecting one or more certain individuals based
on evaluation values of respective individuals, a crossover process of recombining
genes between individuals, and a mutation process of changing genes of any individual,
and the sixth calculation section is configured to generate a pipeline assembling diagram
based on the optimized genes of the individual.
[0030] In addition to the third feature above, the piping diagram creation device in
accordance with the present invention has a fourth feature that the selection process
includes an elite strategy method of extracting an individual with a best evaluation value
from all of the individuals and a tournament method of iterating a process of selecting
an individual with a relatively good evaluation value from any number of individuals
randomly selected from remaining ones of the individuals until a number of individuals
obtained by the selection process equals a number of individuals of a relevant
generation.
Advantageous Effects of Invention
[0031] As described above, the present invention provides a piping diagram creation
method and a piping diagram creation device capable of automatically generating a
piping diagram that can be utilized in actual pipe laying work independently of angles at
branch portions and other factors.
13
Brief Description of Drawings
[0032] Fig. 1A illustrates routes of main and branch pipes connecting specified
intersections, Fig. 1B illustrates a piping diagram generated by a conventional automatic
piping layout device, and Fig. 1C illustrates a piping diagram generated by a piping
diagram creation device of the present invention.
Fig. 2 illustrates the piping diagram creation device according to the present
invention.
Fig. 3 is a flowchart of a piping diagram creation method according to the
present invention.
Fig. 4 is a flowchart of another aspect of the piping diagram creation method
according to the present invention.
Fig. 5 illustrates characteristic evaluation data.
Fig. 6A illustrates specified intersections and control points, and Fig. 6B
illustrates route numbers and intersection numbers.
Fig. 7 illustrates coordinates of the intersections and control points shown in
Fig. 6A and their allowable movement.
Fig. 8 illustrates fittings disposed at intersections.
Fig. 9A illustrates coordinates of control points, and Fig. 9B illustrates
relationship between route numbers and connection points.
Fig. 10 illustrates a piping diagram generated by the piping diagram creation
method of the present invention.
Mode for Carrying out the Invention
[0033] Hereinafter, a piping diagram creation method and a piping diagram creation
device according to the present invention are described with reference to the drawings.
14
[First aspect of the piping diagram creation device]
Fig. 2 is a functional block diagram of the piping diagram creation device 10.
The piping diagram creation device 10 is a device to create a piping diagram (see Figs.
1A-1C) of a pipeline (also referred to as a planned line) that connects a plurality of
intersections IP specified on a map between a start point and an end point and passes
through a control point(s) CP selectively specified between the respective intersections
IP. The piping diagram creation device 10 includes a computer main unit 10A, and
one or more input devices 10B, a display device 10C, a storage device 10D, etc.
connected to the computer main unit 10A.
[0034] A pointing device, such as a mouse, and a keyboard are used as the input
devices 10B, a liquid crystal display is used as the display device 10C, and a hard disk
or the like is used as the storage device 10D. An output device such as a printer is also
connected to the computer main unit 10A, though not shown in the figure.
[0035] The storage device 10D stores information necessary to create pipeline
diagrams, including parts information about parts constituting a pipeline, map
information, and pipeline diagrams created in the past. The parts information includes
types of pipes, such as straight pipes and fittings, and their nominal diameters and pipe
lengths.
[0036] The computer main unit 10A is equipped with a mother board with a CPU, a
memory board, and the like, and an application program for designing pipeline
diagrams is installed in a memory on the memory board. Various functional blocks
described below are implemented as the CPU executes the application program.
[0037] In other words, the computer main unit 10A includes the following functional
blocks: an intersection/control point setting section 11 for setting intersections and
control points on a pipeline diagram layer, a first calculation section 12, a second
15
calculation section 13, a third calculation section 14, a fourth calculation section 15, a
fifth calculation section 16, and a sixth calculation section 17.
[0038] The intersection/control point setting section 11 reads map information of an
area subject to planned pipe laying, which is stored in the storage device 10D, into the
memory (hereinafter referred to as an “internal memory”) on the memory board by an
operator’s operation. The intersection/control point setting section 11 then deploys the
map information on a region serving as a map layer set in the internal memory and
displays it on the display device 10C by the operator’s operation.
[0039] As the operator plots locations for pipe laying on the map displayed on the
display device 10C using a pointing device such as a mouse, coordinates indicative of
the locations are drawn as intersections (IP) on the pipeline diagram layer superimposed
on the map layer and are stored in the internal memory. These intersections include
the intersections IP1, IP2, IP3, IP4 in Fig. 1A described above. Fittings such as bends
and double socket tees are disposed at the respective intersections IP1, IP2, IP3, IP4.
[0040] Straight pipes are used to connect the fittings on the intersections IP.
Preferably, the pipeline is laid to follow the curvature of the road. Thus, a control
point (CP) is indicated on the pipeline diagram layer as an indication point for bending
the straight pipes within a range of a few degrees of bending angle allowed to the
assembling portions of the straight pipes. In response to this indication, the control
point CP is displayed on the pipeline diagram layer similarly to the intersections IP and
stored in the internal memory. In the following description, the intersection IP and the
control point CP may be simply referred to as an “intersection” and a “control point,”
respectively.
[0041] The first calculation section 12 executes a process of selecting fittings to be
disposed on the plurality of intersections set by the intersection/control point setting
16
section 11. In response to the operator selecting each intersection, a pull-down menu
listing available fittings is presented, and in response to a required fitting being selected
by mouse click, the selected fitting is allocated to the intersection.
[0042] The second calculation section 13 determines the number of straight pipes
required, the presence or absence of cut pipes, and the length of cut pipes based on the
distance between the respective intersections and the length of straight pipes. A
distance between the intersections minus the length of the fitting at each intersection is
divided by the length of the straight pipe to find the number of straight pipes required.
The missing length of the calculated number of straight pipes is compensated for by cut
pipes. In this way, the number of straight pipes connecting the respective intersections
and the cut pipe length are determined.
[0043] The third calculation section 14 generates virtual pipelines where the straight
pipes determined by the second calculation section 13 are allocated between the
respective intersections.
Fig. 5 shows a piping diagram connecting an intersection IPA (0, 0), an
intersection IPB (10, 10), and an intersection IPC (20, 10) specified on the xy plane.
The virtual pipeline is identified by characteristic evaluation data, which is expressed as
a sequence of numbers with an assembling angle θi (i is the number of assembling
portions) of assembling portions of the respective straight pipes SP and cut pipes CtP
constituting the virtual pipeline and an adjustment margin Lj (j is the number of the cut
pipes) of the cut pipe length as variables that can be set within a predetermined
allowable range.
[0044] Straight and cut pipes for which the assembling angle θi can be set are those
that are spigot-side joint pipes (starting-point-side joint pipes), other than pipes
connected to fittings and pipes integrated with fittings to prevent bending. Specifically,
17
for a maximum bending angle of ±4° at each joint, the bending angle along the plane is
selected from the options of ±2°, ±1°, and 0°. The angle 0° means straight connection
without bending. The values of the options are not limited to this example and can be
set at any pitch within an angular range smaller than the maximum bending angle of
±4°.
[0045] The adjustment margin Lj for the cut pipe length is the length to adjust the
length Lc of the cut pipe obtained by the aforementioned calculation, and the adjusted
length is Lc + Lj. The equation of Lj = ΔL × d is set for Lj, where ΔL is set to 0.01 m
and d is selected from the options of ±2, ±1, and 0. That is, Lj is any one of ±2 cm, ±1
cm, and 0 cm. Although ΔL = 0.01 m is given as an example in the present
embodiment, the value of ΔL is not limited to any value. Also, the values of the
options d are not limited to this example.
[0046] In the piping diagram shown in Fig. 5, the characteristic evaluation data is
expressed as a sequence of numbers [θ1, θ2, θ3, L1, θ4, θ5, L2]. By selecting each of
the variables θ1, θ2, θ3, L1, θ4, θ5, L2 from the above options, it is possible to define
piping diagrams in five factorial ways.
[0047] The fourth calculation section 15 calculates a first characteristic value CV1, a
second characteristic value CV2, a third characteristic value CV3, and a fourth
characteristic value CV4 for virtual pipelines for which each of the variables θ1, θ2, θ3,
L1, θ4, θ5, L2 of the characteristic evaluation data is set to any value within a
predetermined allowable range, namely, in the present embodiment, for each virtual
pipeline identified by the characteristic evaluation data with the variables appropriately
selected from the above options.
[0048] The first characteristic value CV1 is a value identified by a difference value
between the total number of intersections and control points and the number of
18
intersections and control points each having an error, which is defined as an amount of
misalignment between the virtual pipeline and each intersection and between the virtual
pipeline and each control point, at or below a predetermined threshold, the latter number
being a continuous count from the start point. The smaller the difference value
defining the first characteristic value CV1, the less misalignment the virtual pipeline is
evaluated to have.
[0049] Following a conventional design approach of manually operating a piping
diagram creation device to design a piping diagram, the above approach of using the
difference value focuses on a procedure of sequentially arranging pipe materials along a
planned line from a start point such that errors at the intersections and control points are
within a threshold.
[0050] In the present embodiment, the threshold is set to 0.3 m. However, the
threshold is not limited to 0.3 m and can be set to any value depending on actual
situations. Although the same threshold is set for all intersections and control points,
different thresholds may be set for the intersections and control points, or a different
threshold may be set for each of the intersections and control points. This is because
doing so facilitates flexible adaptation to the surrounding environment or other factors
of the pipe laying site.
[0051] The second characteristic value CV2 is a value identified by an error at the
intersection or control point that first exceeded the threshold. As with the first
characteristic value CV1, the smaller the error defining the second characteristic value
CV2, the smaller the degree of deviation from the threshold at the intersections and
control points in the virtual pipeline, so that such a virtual pipeline can be evaluated to
have a smaller probability that the subsequent placement of pipe materials will be
displaced significantly from the planned line.
19
[0052] The third characteristic value CV3 is a value identified by an average value of
errors at the intersections and control points where the errors are at or below the
threshold. The smaller the average value of the errors defining the third characteristic
value CV3, the less misalignment along the planned line the virtual pipeline is evaluated
to have.
[0053] The fourth characteristic value CV4 is a value identified by the proportion of
the number of assembling portions with the assembling angle θi of other than 0 degrees,
within the range from the start point to the intersections (IP) and the control points (CP)
where the errors are at or below the threshold. The smaller the proportion defining the
fourth characteristic value CV4, the greater linearity with less fluctuations the pipeline
is evaluated to have.
[0054] Further, the fourth calculation section 15 calculates an evaluation value EV
shown in the following equation from the characteristic values CV1 to CV4.
EV = CV1 × S1 + CV2 × S2 + CV3 × S3 + CV4 × S4
The weighting factors S1, S2, S3, S4 are used to adjust the contributions of the
respective characteristic values CV1, CV2, CV3, CV4 for evaluation of each virtual
pipeline defined by the characteristic evaluation data. These weighting factors are set
depending on which of the characteristic values CV1, CV2, CV3, CV4 is given more
importance. In the present embodiment, the weighting factors S1, S2, S3 are set to 1,
and the weighting factor S4 is set to 0.2. However, the weighting factors are not
limited to any values.
[0055] The fifth calculation section 16 selects one virtual pipeline from the virtual
pipelines based on the evaluation values EV for the respective virtual pipelines
calculated by the fourth calculation section 15. Specifically, the fifth calculation
section 16 selects a virtual pipeline with the smallest evaluation value EV.
20
[0056] The sixth calculation section 17 generates a pipeline assembling diagram based
on the sequence of numbers [θ1, θ2, θ3, L1, θ4, θ5, L2] defining the characteristic
evaluation data of the virtual pipeline selected by the fifth calculation section 16.
[0057] Finding the evaluation values EV for all settable characteristic evaluation data
would lead to an increased calculation load. Thus, setting a threshold that limits a
range of values that can be used as the characteristic evaluation data can inhibit an
increase in the calculation load. It should be noted that a configuration is also possible
where the fourth calculation section 15 finds the evaluation values EV for all settable
characteristic evaluation data, and a pipeline assembling diagram is generated based on
the characteristic evaluation data with the smallest evaluation value EV.
[0058] The piping diagram creation method according to the present embodiment is
described with reference to Fig. 3.
The road map deployed on the map layer by the intersection/control point
setting section 11 is displayed on the display device 10C (SA1). The intersections IP
at which the fittings are to be disposed are indicated on the pipeline diagram layer
superimposed on the map layer, and also the control points CP at which the straight
pipes are to be bent are indicated on the pipeline diagram layer (SA2).
[0059] Then, the first calculation section 12 selects the fittings to be disposed at the
plurality of intersections IP and allocates the fittings at the respective intersections IP
(SA3).
The first calculation section 12 determines in advance whether it is possible to
carry out the pipe laying according to a piping layout that extends along a straight line
connecting the respective intersections IP, based on the shapes of the fittings to be
disposed at the respective intersections IP or the presence/absence of the control points
CP specified between the respective intersections IP. If it is possible to carry out the
21
pipe laying (SA4, OK), the process moves to the step of executing the automatic piping
layout process. The automatic piping layout process is a process of calculating the
number of straight pipes required and the length of the cut pipes based on the distance
along the straight line connecting the respective intersections IP and generating a piping
diagram in which the calculated straight and cut pipes are connected to the fittings at the
intersections IP. The results of the automatic piping layout process is stored in the
storage device 10D at step SA11.
[0060] The determination of whether it is possible to carry out the pipe laying
according to the piping layout along the straight line connecting the respective
intersections IP is made based on whether the sockets of the fittings at the intersections
IP are aligned with the extending direction of the straight line connecting the respective
intersections IP. If the sockets are aligned with the extending direction, it is
determined that such pipe laying can be carried out; if the sockets are not aligned with
the extending direction, it is determined that the pipe laying cannot be carried out. If
the pipe laying cannot be carried out (SA4, NG), the process moves to a process of
generating virtual pipelines.
[0061] At step SA5, the second calculation section 13 determines the number of
straight pipes required, the presence/absence of the cut pipes, and the length of the cut
pipes based on the distance between the respective intersections and the length of the
straight pipes. Further, the third calculation section 14 generates virtual pipelines
based on the characteristic evaluation data described above (SA6), and the fourth
calculation section 15 sets values selected from a predefined table of options for the
variables constituting the characteristic evaluation data (SA7).
[0062] The table of options is a table that presents options for the respective variables
θ1, θ2, θ3, L1, θ4, θ5, L2 of the characteristic evaluation data, and presents values that
22
can be selected as any values falling within a predetermined allowable range. In the
above example, the values ±2°, ±1°, and 0° are the options for the assembling angle θi,
and the values ±2 cm, ±1 cm, and 0 cm are the options for the adjustment margin Lj of
the cut pipe length.
[0063] Further, the fourth calculation section 15 iterates the process of calculating the
evaluation value EV of each virtual pipeline with the characteristic evaluation data
selected at step SA7 for all options set in the table of options, and the fifth calculation
section 16 selects one virtual pipeline that is defined by the characteristic evaluation
data with the smallest evaluation value, from all evaluation values EV calculated by the
fourth calculation section 15 (SA7, SA8).
[0064] The sixth calculation section 17 generates a pipeline assembling diagram
(piping diagram) based on the characteristic evaluation data of the one virtual pipeline
selected by the fifth calculation section 16 (SA9), and the piping diagram is stored in
the storage device 10D (SA11).
[0065]
[Second aspect of the piping diagram creation device]
A second aspect of the piping diagram creation device 10 is described below.
The below description focuses on differences from the above first aspect, and
description of components similar to those in the first aspect will be omitted.
In the first aspect, the third calculation section 14 and the fourth calculation
section 15 iterate the process of updating the characteristic evaluation data and
calculating and evaluating the evaluation values. The second aspect differs in that a
plurality of instances of the characteristic evaluation data are generated in advance, and
the characteristic evaluation data is optimized using genetic algorithms GA.
[0066] That is, the third calculation section 14 generates virtual pipelines identified by
23
a plurality of individuals each having, as genes, the assembling angle θi (i is the number
of assembling portions) of the assembling portions of the respective straight pipes
constituting the virtual pipeline and the adjustment margin Lj (j is the number of cut
pipes) of the cut pipe length.
[0067] The characteristic evaluation data expressed by the above sequence of numbers
[θ1, θ2, θ3, L1, θ4, θ5, L2] is an individual, and the variables θ1, θ2, θ3, L1, θ4, θ5, L2
are considered as genes. In the present embodiment, the number of individuals of a
first generation is set to 300. However, the number of individuals is not limited to any
value and is set as appropriate.
[0068] For each individual generated by the third calculation section 14, the fourth
calculation section 15 calculates the characteristic values CV1-CV4 and the evaluation
value EV based on the characteristic values CV1-CV4, in the same manner as in the
above first aspect.
[0069] The fifth calculation section 16 executes the genetic algorithms that iterate a
generation change process including a selection process of selecting certain individuals
based on the evaluation value EV of each individual and, as part of the selection process,
including either or both a crossover process of recombining genes between individuals
and a mutation process of changing genes of any individual. The fifth calculation
section 16 thus generates an individual with optimized genes having an excellent
evaluation value.
[0070] The selection process performed by the fifth calculation section 16 includes an
elite strategy method of extracting an individual with the best evaluation value EV (i.e.,
the smallest evaluation value EV) from the individuals and a tournament method of
iterating a process of selecting an individual with a relatively good evaluation value EV
from any number of individuals randomly selected from the remaining individuals until
24
the number of process iterations equals the number of individuals of the generation.
The crossover process includes a process of taking adjacent even-numbered and
odd-numbered individuals with a certain probability and performing crossover of genes
by a two-point crossover method. The mutation process includes a process of selecting a
certain proportion of individuals with lesser evaluation values from the individuals and
setting all genes thereof to zero and a process of swapping any adjacent genes of an
individual extracted with a certain probability.
[0071] The fifth calculation section 16 performs the generation change process up to a
predetermined generation and selects, as one best virtual pipeline, an individual with the
smallest evaluation value EV from individuals of the last generation.
[0072] The sixth calculation section 17 generates a pipeline assembling diagram
(piping diagram) based on genes of the individual selected as the one virtual pipeline by
the fifth calculation section 16.
[0073] Fig. 4 shows a procedure of the piping diagram creation method of the second
aspect. Steps SB6-SB9 differ from the procedure of the piping diagram creation
method shown in Fig. 3, and the rest of the steps is identical thereto.
At step SB5, the second calculation section 13 determines the number of
straight pipes required, the presence or absence of cut pipes, and the length of cut pipes
based on the distance between the respective intersections and the length of straight
pipes.
[0074] Further, the third calculation section 14 generates virtual pipes of 300
individuals of the first generation defined by the characteristic evaluation data (SB6).
The fourth calculation section 15 calculates the evaluation value EV of each individual
(SB7), and the fifth calculation section 16 performs the generation change process
(SB8).
25
[0075] The evaluation value calculation process at step SB7 and the generation change
process at step SB8 are iterated until the generation change process reaches a pre-set
number of generations (40 generations in the present embodiment). Upon completion
of the evaluation value calculation process up to the pre-set number of generations, a
virtual pipeline with the smallest evaluation value EV is selected as one best virtual
pipeline, from virtual pipelines of 300 individuals of the last generation (SB8, OK), and
a piping diagram is generated based on the characteristic evaluation data of the one
virtual pipeline (SB9).
[0076]
[Generation change process]
The generation change process is now detailed.
The genes of individuals INm of the Nth generation are expressed as [θ1Nm,
θ2Nm, θ3Nm, L1Nm, θ4Nm, θ5Nm, L2Nm], where m is the number of individuals, i.e., the
population.
First, an evaluation value EV1m is calculated for respective genes [θ11m, θ21m,
θ31m, L11m, θ41m, θ51m, L21m] of m individuals I1m of the first generation.
[0077] First, a selection process employing an elite strategy method and a tournament
method is performed. The elite strategy method refers to a process of unconditionally
extracting, as an individual of the next generation, one individual with the smallest
evaluation value EV1m from m individuals I1m of the first generation. The tournament
method refers to a process of iterating the selecting of an individual(s) (one individual
in the present embodiment) with a relatively good evaluation value EV from any
number (three in the present embodiment) of individuals randomly selected from m
individuals I1m of the first generation until the number of process iterations equals the
population (number of individuals) of the generation. An individual with a smaller
26
evaluation value EV1m is determined to have a greater fitness. It is preferable that
about three individuals be selected for comparison, but the number of individuals to be
selected is not limited to this value and can be set as appropriate. Also, the number of
individuals to be selected as an individual(s) with a relatively good evaluation value EV
is not limited to one, and a plurality of individuals may be selected as individuals with a
relatively good evaluation value EV, in relation to the number of individuals selected for
comparison.
[0078] Through the selection process, individuals with a larger evaluation value EV1m,
i.e., with a lower fitness, are eliminated, resulting in individuals with a greater fitness
surviving into the next generation. In the present embodiment, the selection is iterated
such that the number of selected individuals equals the population (number of
individuals), resulting in the same number of individuals as those of the first generation.
Roulette or other selection methods may be employed in the selection process, instead
of the tournament method.
[0079] Then, individuals selected through the selection process are subjected to a
crossover process, in which adjacent even-numbered and odd-numbered individuals are
taken with a certain probability and genes are crossed over by a two-point crossover
method. In the present embodiment, the probability of the crossover is set to 70%.
Thus, 30% of the individuals that survived through the selection process will remain as
they are.
[0080] First and second mutation processes are performed on the individuals having
undergone the crossover process. The first mutation process, which is a modified
version of the inversion method, swaps any adjacent genes of an individual extracted
with a certain probability (30% in the present embodiment). The number of swaps is
not limited to one and can be set as appropriate depending on the number of genes.
27
Note that the inversion method is a method of inverting the order of two random genes.
[0081] Swapping arbitrarily selected genes has a large effect on the entire pipeline,
which would make it difficult to improve the evaluation value even after generational
changes. However, swapping adjacent genes allows for fine adjustment while
reducing the effect on the entire pipeline. The predetermined probability is not limited
to 30% and can be adjusted as appropriate.
[0082] The second mutation process is a process of selecting a certain proportion
(15% in the present embodiment) of individuals with a lesser evaluation value from the
individuals and setting all genes of the selected individuals to zero. In the present
embodiment a “lesser evaluation value” means a larger evaluation value.
[0083] Through the mutation process of setting all genes of a certain proportion of
individuals with lesser evaluation values to zero, virtual pipelines with genes exhibiting
straight pipeline shapes can survive into the next generation at a certain ratio. In the
context of generating a straight pipeline, iterating such a process can generate a pipeline
having excellent linearity with less fluctuations, rather than a straight pipeline that has
many fluctuations with repeated minor curvatures. The certain proportion is not
limited to 15% and can be adjusted as appropriate.
[0084] Thus, genes [θ12m, θ22m, θ32m, L12m, θ42m, θ52m, L22m] of individuals I2m of the
second generation are generated, and the same process is iterated.
[0085]
[Third aspect of the piping diagram creation device]
In a third aspect, the characteristic values calculated by the fourth calculation
section 15 are different from those described in the above first and second aspects.
[0086] The fourth calculation section 15 calculates an evaluation value, i.e., a fitness,
of each virtual pipeline obtained by setting the variables θ1, θ2, θ3, L1, θ4, θ5, L2 of the
28
characteristic evaluation data to any values falling within a predetermined allowable
range, based on a fifth characteristic value CV5, a sixth characteristic value CV6, and a
seventh characteristic value CV7, where the fifth characteristic value CV5 is a
cumulative value of errors between each intersection and a position on each virtual
pipeline corresponding to each intersection, the sixth characteristic value CV6 is a
cumulative value of the number of assembling portions with an assembling angle of
other than 0 degrees, and the seventh characteristic value CV7 is a cumulative value of
distances between each control point and each virtual pipeline.
[0087] The fifth characteristic value CV5 is expressed as CV5 = Σ(ΔEip), where ΔEip is
an error between an intersection and a position on each virtual pipeline corresponding to
the intersection, and the accumulated error value for all intersections is the fifth
characteristic value CV5. The smaller the accumulated error value, the greater fitness
the virtual pipeline is determined to have.
[0088] The sixth characteristic value CV6 is expressed as CV6 = Σ(Jf), where Jf
represents bent joints, and the total number of bent joints is the sixth characteristic value
CV6. The fewer the number of bent joints, the greater fitness the virtual pipeline is
determined to have.
[0089] The seventh characteristic value CV7 is expressed as CV7 = Σ(Dpp), where Dpp
is a separation distance between a control point and the pipeline (the shortest distance
between the control point and the pipeline). The total value of separation distances
between the control points and the pipeline is the seventh characteristic value CV7.
The smaller the total value of the separation distances between the control points and
the pipeline, the greater fitness the virtual pipeline is determined to have because the
virtual pipeline will pass through positions closer to the control points.
[0090] The evaluation value EV of each virtual pipeline is expressed as a sum of
29
products of the characteristic values by predetermined weighting factors for the
respective characteristic values, resulting in an equation of EV = CV5 × S5 + CV6 × S6
+ CV7 × S7. The weighting factors S5, S6, S7 are used to adjust the contributions of
the respective characteristic values CV5, CV6, CV7 for evaluation of each virtual
pipeline defined by the characteristic evaluation data. These weighting factors are set
depending on which of the characteristic values CV5, CV6, CV7 is given more
importance. For example, when the intersection positions are given more importance,
the weighting factor S5 will be set to a larger value than the other weighting factors S6
and S7.
[0091] The above seventh characteristic value CV7 is an evaluation item that is used
when a control point(s) is set. When no control point is set, only the fifth
characteristic value CV5 and the sixth characteristic value CV6 will be used for
evaluation. It is also possible to only use the fifth characteristic value CV5 and the
sixth characteristic value CV6 for evaluation when few control points are set.
[0092] That is, the piping diagram creation method of the third aspect includes: a step
of calculating an evaluation value of each virtual pipeline obtained by setting variables
of the characteristic evaluation data to any values falling within a predetermined
allowable range, based on the fifth characteristic value CV5 and the sixth characteristic
value CV6, where the fifth characteristic value CV5 is a cumulative value of errors
between each intersection and a position on each virtual pipeline corresponding to each
intersection, and the sixth characteristic value CV6 is a cumulative value of the number
of assembling portions with an assembling angle of other than 0 degrees; and a step of
generating a pipeline assembling diagram based on the characteristic evaluation data of
a virtual pipeline that has an evaluation value at or below a predetermined threshold
from among the virtual pipelines.
30
[0093] Preferably, the evaluation value calculated at the step of calculating the
evaluation value of each virtual pipeline further includes the seventh characteristic value
CV7, which is a cumulative value of separation distances between each virtual pipeline
and each control point.
[0094]
[Fourth aspect of the piping diagram creation device]
The fourth aspect is a somewhat modified version of the above third aspect.
That is, the fourth calculation section 15 calculates an evaluation value, i.e., a
fitness, of each virtual pipeline obtained by setting variables θ1, θ2, θ3, L1, θ4, θ5, L2
of the characteristic evaluation data to any values falling within a predetermined
allowable range, based on an eighth characteristic value, a ninth characteristic value,
and a tenth characteristic value, where the eighth characteristic value is an average value
of errors between each intersection and a position on each virtual pipeline
corresponding to each intersection, the ninth characteristic value is a ratio of the number
of assembling portions with an assembling angle of other than 0 degrees to the total
number of assembling portions, and the tenth characteristic value is an average value of
distances between each control point and each virtual pipeline.
[0095] In the first to third aspects described above, a virtual pipeline is generated
based on the single instance of the characteristic evaluation data over the entire region
of the pipeline layer on which the intersections are specified, and that virtual pipeline is
evaluated. However, in cases where the pipeline includes branch points, a virtual
pipeline based on the characteristic evaluation data may be generated and evaluated for
each pipeline connecting the branch points.
Example
31
[0096]
An example of the piping layout process using the genetic algorithms GA of
the second aspect is described below.
Fig. 6A shows intersections and control points specified on the pipeline
diagram layer and a pipeline (indicated by dashed lines) connecting the intersections
with straight lines. Fig. 6B shows identification codes of the intersections constituting
a main pipeline (route 1) and branch pipelines (routes 2 and 3) branching off of the main
pipeline.
[0097] Fig. 7 shows the route numbers and intersection numbers shown in Fig. 6B, x,
y coordinates of each intersection, and allowable movement (1 m). The virtual
pipelines finally obtained at step SB7 in Fig. 4 are the virtual pipelines wherein each
intersection is within the allowable movement limit. Fig. 8 shows a list of fittings
disposed at the respective intersections. Blanks other than those associated with the
start and end points represent that bends are to be disposed.
[0098] Fig. 9A shows x, y coordinates of the specified control points and a route
including the control points. Fig. 9B shows route connection information indicating
whether and to which intersection a tee (branch pipe) should be connected to, if any.
[0099] When intersections and control points are set using the above
intersection/control point setting section 11, values shown in Figs. 7-9B are entered.
[0100] Fig. 10 shows results of the piping layout process for the pipeline with such
intersections and control points, using the genetic algorithms GA of the second aspect.
White circles represent the control points, and black circles represent the assembling
portions of the pipeline. With the number of individuals of the first generation set to
300 and the number of generations set to 40, it takes a few seconds to generate a piping
diagram with a total length of about 100 m using about 20 pipe materials. As such, an
32
extremely efficient process is enabled compared to manually inputting the piping
diagram shown in Fig. 10, which would take several hours. Note that the piping
diagram shown in Fig. 10 is merely an example and does not represent the best piping
diagram.
[0101] The above embodiment illustrates certain aspects of the present embodiment.
It will be readily appreciated that the descriptions of the embodiment do not limit the
technical scope of the present invention, and various changes and modifications can be
made as appropriate to the extent that such changes and modifications still provide the
functions and benefits of the present invention.
Reference Signs List
[0102] 10 Piping diagram creation device
10A Computer main unit
10B Input device
10C Display device
10D Storage device
11 Intersection/control point setting section
12 First calculation section
13 Second calculation section
14 Third calculation section
15 Fourth calculation section
16 Fifth calculation section
17 Sixth calculation section
33
WE CLAIM:-
1. A piping diagram creation method for creating a piping diagram of a pipeline
connecting a plurality of intersections (IP) specified on a map between a start point and
an end point and passing through a control point (CP) selectively specified between the
respective intersections (IP), the method comprising:
a first step of selecting fittings to be disposed at the respective intersections
(IP);
a second step of determining a number of straight pipes required, presence or
absence of cut pipes, and a length of the cut pipes, based on a distance between the
respective intersections (IP) and a length of the straight pipes;
a third step of generating virtual pipelines on which the straight pipes and the
cut pipes determined at the second step are allocated between the respective
intersections (IP), each of the virtual pipelines being identified by characteristic
evaluation data expressed as a sequence of numbers with an assembling angle θi (i is a
number of assembling portions) of assembling portions of the respective straight pipes
and cut pipes constituting the virtual pipeline and an adjustment margin Lj (j is a
number of cut pipes) of the cut pipe length as variables that are settable within a
predetermined allowable range;
a fourth step of calculating an evaluation value of each of the virtual pipelines
generated at the third step based on
(1) a first characteristic value identified by a difference value between
a total number of intersections (IP) and control points (CP) and a number of
intersections (IP) and control points (CP) each having an error at or below a
predetermined threshold, the latter number being a continuous count from the start point,
the error being defined as an amount of misalignment between the virtual pipeline and
34
each intersection (IP) and between the virtual pipeline and each control point (CP),
(2) a second characteristic value identified by the error at one of the
intersections (IP) or the control point (CP) that first exceeds the threshold,
(3) a third characteristic value identified by an average value of the
errors at the intersections (IP) and the control point (CP) having the errors at or below
the threshold, and
(4) a fourth characteristic value identified by a proportion of a number
of assembling portions with the assembling angle θi of other than 0 degrees, within a
range from the start point to the intersections (IP) and the control point (CP) having the
errors at or below the threshold;
a fifth step of selecting one virtual pipeline from the virtual pipelines based on
the evaluation value; and
a sixth step of generating a pipeline assembling diagram based on characteristic
evaluation data of the virtual pipeline selected at the fifth step.
2. The piping diagram creation method according to claim 1, wherein
the evaluation value is a sum of products of the respective characteristic values
by predetermined weighting factors for the respective characteristic values.
3. The piping diagram creation method according to claim 1 or 2, wherein
the third step includes forming the respective virtual pipelines from individuals
including, as genes, the assembling angle θi (i is the number of assembling portions) of
the assembling portions of the respective straight pipes and cut pipes and the adjustment
margin Lj (j is the number of cut pipes) of the cut pipe length,
the fifth step includes executing a genetic algorithm to generate an individual
35
with optimized genes, the genetic algorithm iterating a generation change process
including any of a selection process of selecting one or more certain individuals based
on evaluation values of respective individuals, a crossover process of recombining
genes between individuals, and a mutation process of changing genes of any individual,
and
the sixth step includes generating a pipeline assembling diagram based on the
optimized genes of the individual.
4. The piping diagram creation method according to claim 3, wherein
the selection process includes an elite strategy method of extracting an
individual with a best evaluation value from all of the individuals and a tournament
method of iterating a process of selecting an individual with a relatively good evaluation
value from any number of individuals randomly selected from remaining ones of the
individuals until a number of individuals obtained by the selection process equals a
number of individuals of a relevant generation.
5. The piping diagram creation method according to claim 3 or 4, wherein
the crossover process includes a process of taking adjacent even-numbered and
odd-numbered ones of the individuals with a certain probability and performing
crossover of genes by a two-point crossover method.
6. The piping diagram creation method according to any one of claims 3 to 5,
wherein
the mutation process includes a process of selecting a certain proportion of
individuals with lesser evaluation values from the individuals and setting all genes
36
thereof to zero.
7. The piping diagram creation method according to any one of claims 3 to 6,
wherein
the mutation process includes a process of swapping any adjacent genes of an
individual extracted with a certain probability from the individuals.
8. The piping diagram creation method according to any one of claims 1 to 7,
further comprising a pre-determination step of determining in advance whether it is
possible to carry out a piping layout along a straight line connecting respective
intersections (IP), based on shapes of fittings to be disposed at the respective
intersections (IP) or presence/absence of a control point (CP) specified between the
respective intersections (IP), wherein
upon determination at the pre-determination step that it is impossible to carry
out the piping layout along the straight line connecting the intersections (IP), the second
to sixth steps are performed.
9. A piping diagram creation device for creating a piping diagram of a pipeline
connecting a plurality of intersections (IP) specified on a map between a start point and
an end point and passing through a control point (CP) selectively specified between the
respective intersections (IP), the device comprising:
a first calculation section configured to select fittings to be disposed at the
respective intersections (IP);
a second calculation section configured to determine a number of straight pipes
required, presence or absence of cut pipes, and a length of the cut pipes, based on a
37
distance between the respective intersections (IP) and a length of the straight pipes;
a third calculation section configured to generate virtual pipelines on which the
straight pipes and the cut pipes determined by the second calculation section are
allocated between the respective intersections (IP), each of the virtual pipelines being
identified by characteristic evaluation data expressed as a sequence of numbers with an
assembling angle θi (i is a number of assembling portions) of assembling portions of the
respective straight pipes and cut pipes constituting the virtual pipeline and an
adjustment margin Lj (j is a number of cut pipes) of the cut pipe length as variables that
are settable within a predetermined allowable range;
a fourth calculation section configured to calculate an evaluation value of each
of the virtual pipelines generated by the third calculation section based on
(1) a first characteristic value identified by a difference value between
a total number of intersections (IP) and control points (CP) and a number of
intersections (IP) and control points (CP) each having an error at or below a
predetermined threshold, the latter number being a continuous count from the start point,
the error being defined as an amount of misalignment between the virtual pipeline and
each intersection (IP) and between the virtual pipeline and each control point (CP),
(2) a second characteristic value identified by the error at one of the
intersections (IP) or the control point (CP) that first exceeds the threshold,
(3) a third characteristic value identified by an average value of the
errors at the intersections (IP) and the control point (CP) having the errors at or below
the threshold, and
(4) a fourth characteristic value identified by a proportion of a number
of assembling portions with the assembling angle θi of other than 0 degrees, within a
range from the start point to the intersections (IP) and the control point (CP) having the
38
errors at or below the threshold;
a fifth calculation section configured to select one virtual pipeline from the
virtual pipelines based on the evaluation value;
a sixth calculation section configured to generate a pipeline assembling
diagram based on characteristic evaluation data of the virtual pipeline selected by the
fifth calculation section.
10. The piping diagram creation device according to claim 9, wherein
the evaluation value is a sum of products of the respective characteristic values
by predetermined weighting factors for the respective characteristic values.
11. The piping diagram creation device according to claim 9 or 10, wherein
the third calculation section is configured to form the respective virtual
pipelines from individuals including, as genes, the assembling angle θi (i is the number
of assembling portions) of the assembling portions of the respective straight pipes and
cut pipes and the adjustment margin Lj (j is the number of cut pipes) of the cut pipe
length,
the fifth calculation section is configured to execute a genetic algorithm to
generate an individual with optimized genes, the genetic algorithm iterating a generation
change process including any of a selection process of selecting one or more certain
individuals based on evaluation values of respective individuals, a crossover process of
recombining genes between individuals, and a mutation process of changing genes of
any individual, and
the sixth calculation section is configured to generate a pipeline assembling
diagram based on the optimized genes of the individual.
39
12. The piping diagram creation device according to claim 11, wherein
the selection process includes an elite strategy method of extracting an
individual with a best evaluation value from all of the individuals and a tournament
method of iterating a process of selecting an individual with a relatively good evaluation
value from any number of individuals randomly selected from remaining ones of the
individuals until a number of individuals obtained by the selection process equals a
number of individuals of a relevant generation.

Documents

Application Documents

# Name Date
1 202227067262.pdf 2022-11-23
2 202227067262-TRANSLATIOIN OF PRIOIRTY DOCUMENTS ETC. [23-11-2022(online)].pdf 2022-11-23
3 202227067262-STATEMENT OF UNDERTAKING (FORM 3) [23-11-2022(online)].pdf 2022-11-23
4 202227067262-PROOF OF RIGHT [23-11-2022(online)].pdf 2022-11-23
5 202227067262-PRIORITY DOCUMENTS [23-11-2022(online)].pdf 2022-11-23
6 202227067262-POWER OF AUTHORITY [23-11-2022(online)].pdf 2022-11-23
7 202227067262-FORM 1 [23-11-2022(online)].pdf 2022-11-23
8 202227067262-FIGURE OF ABSTRACT [23-11-2022(online)].pdf 2022-11-23
9 202227067262-DRAWINGS [23-11-2022(online)].pdf 2022-11-23
10 202227067262-DECLARATION OF INVENTORSHIP (FORM 5) [23-11-2022(online)].pdf 2022-11-23
11 202227067262-COMPLETE SPECIFICATION [23-11-2022(online)].pdf 2022-11-23
12 202227067262-FORM 18 [06-12-2022(online)].pdf 2022-12-06
13 Abstract1.jpg 2022-12-28
14 202227067262-FORM 3 [17-05-2023(online)].pdf 2023-05-17
15 202227067262-FORM 3 [01-12-2023(online)].pdf 2023-12-01
16 202227067262-FER.pdf 2025-11-12

Search Strategy

1 202227067262_SearchStrategyNew_E_SearchpipingE_12-09-2025.pdf