Method Of Precasting Track Support Sleepers On A Precast Span

Systra
Refused App No 519/KOL/2009 Mechanical Engineering

Patent information

IP India · live record
Application number
519/KOL/2009
Filing date
23 March 2009
Status
Refused
Publication number
18/2010
Publication type
INA
Invention field
Mechanical Engineering

Abstract

The method includes: - A step of positioning the track during which dummy rails (5) having the same profile as those to be placed on site are arranged in the span (2) in accordance with the position of the final rails, - A step of setting in place re-entrants of the systems of fastening rails to the span (2) during which re-entrant moulds (8) of dimension corresponding to those of the systems of fastening are fixed to the dummy rails (5), at the positions of the systems of fastening, and A step of realising sleepers during which the armouring of the sleepers are set into place, the formwork (12) is carried out and the concrete is poured.

Applicants

1
France
SYSTRA 5, AVENUE DU COQ, 75009 PARIS

Inventors

2
France
DUTOIT DANIEL101 BIS, BOULEVARD JEAN JAURÈS, 92100 BOULOGNE-BILLANCOURT
France
JACQUIER PATRICE9, ALLÈE DES PINS, 95270 SEUGY

Specification

Show full textCollapse

METHOD FOR PRECASTING TRACK SUPPORT SLEEPERS ON A PRECAST SPAN This invention relates to a method of precasting track support sleepers, in particular on a precast structure for delimiting tracks, such as full precast U-shaped spans used during the realisation of railway viaducts. It also relates to a method for laying rails on a span equipped with precast sleepers. A method for laying rails on precast spans is known. According to this method, in a first step, carried out are the installation of the main points representing the axis of the track installed in the span, then that of the secondary points and the realisation of the rejection pegging out, in a second step the rails are supplied then welded and provided with their means of fastening to the span, in a third step adjusting gauges are set in place and the provided rails are prepositioned on the latter, in a fourth step, the armouring of the sleepers are set into place, the track is adjusted, the formwork is realised and the concrete is poured, and in a fifth step, the track is again verified and the formwork is removed.

Such a method, although it does meet the requirements in terms of civil engineering, is rather inconvenient due to the fact that the substantial concreting of the sleepers is performed on site, which, in particular, takes up a considerable amount; of time, and is subject to the scheduling constraints concerning the project as a whole, and imposes constraints on the project. This invention aims to realise a new method making it possible to overcome the aforementioned disadvantages. The invention as such includes a method of precasting track support sleepers on a precast span, including a step of positioning the track during which dummy rails having the same profile as those to be installed on site are arranged on the span in accordance with the position of the final rails, a step of setting up re-entrants of systems of fastening rails to the span during which are fixed to the rails, to the positions of the systems of fastening, re-entrant moulds with dimensions corresponding to those of the systems of fastening, and a step of realising sleepers during which the armouring of the sleepers are set into place, the formwork is carried out and the concrete is poured. The main advantage of such a method is that it can be carried out in the factory. As such, the conditions for implementing concrete are clearly more favourable: climatic influences are reduced, and even suppressed; the concrete is made on the site, which suppresses transit time, and reduces, and even suppresses, the use

of additives such as retarders or fluidifiers (for the pumping) ; the control of quality is improved due to the very fact of being carried out in the factory. In addition, the realisation of sleepers is disconnected from the progress of the project, which makes it possible to remove the construction of the track support sleepers from the critical path of the realisation of the project in relation to a conventional method of realisation. The invention also includes a method for laying rails on a span equipped with precast sleepers, including a step of setting up rails during which the rails, provided with systems of fastening, are correctly arranged in relation to the span, and a step of sealing during which the systems of fastening of the rails are sealed to the span by concreting in the re-entrants made in the sleepers. As such, the works on the site are greatly simplified, resulting in substantial savings in scheduling in the placing of track and over the entire project. In addition, it is still possible to adjust, on site, the placing of the tracks of great length, and, as required, to concrete the track once the rails have been adjusted. Finally, the two methods make it possible to reduce the cost of realising the track in concrete (in linear metres). The invention also relates to a method of setting up, on site, rails on precast spans, including a first step of precasting, more preferably in the factory, of sleepers on the precast spans, followed by a second

step, on site, of placing rails on the span provided with precast sleepers. Other particularities and advantages of this invention shall appear in the embodiment provided by way of a non-limited example and shown in the annexed drawings wherein: Figure 1 is a schematic cross-section view of a precast span; Figure 2 is a view similar to figure 1, of the dummy rails being arranged in accordance with the positions of the corresponding final rails on site; Figure 3 is a schematic cross-section view, of a dummy rail provided with a re-entrant mould and set in place in the formwork of a sleeper; Figure 4 is a schematic top view corresponding to figure 3; Figure 5 is a view similar to figure 3, after form removal and removal of the dummy rail; Figure 6 is a schematic top view corresponding to figure 5; Figure 7 is a schematic cross-section view of a span provided with precast sleepers, with the final rails being correctly positioned; Figure 8 is a schematic cross-section view, of a final rail provided with a system of fastening which is set in place in a re-entrant of a sleeper; Figure 9 is a view similar to figure 8 after sealing of the system of fastening to the sleeper. Generally, the general process of placing rails 1 on a precast span 2 includes a method of precasting track support sleepers 3 on a precast span 2, followed,

on site, by a method of fastening rails 1 on the span 2 provided with sleepers 3, realised in accordance with the aforementioned method. The method of precasting sleepers 3 is carried out, more preferably, in the factory due to the many advantages that are inherent to the technical possibilities available in the factory. It could however be carried out, as required, on site, the precasting of the sleepers 3 however being realised before the setting in place of the span on its site dedicated to it. The method of precasting is particularly adapted to the spans 2 used for the realisation of railway viaducts, in particular to full spans (extending from one pier to the other of the viaduct), self-supporting and U-shaped. This method includes a step of layout drawing. During this step a layout drawing of the span 2 as well as of the joints from the span to the abutments is carried out. This layout drawing that is proper to each span in question (carried out, for example, on a A3-format sheet) comprises an outline sketch of the span, with the joints to the abutments, rails 3, positions of the systems of fastening of rail 4, as well as various particular equipment concerning this span, such as a cable crossing. It also comprises the indications of horizontal, profile in length and elevation alignment. This layout drawing makes it possible to know the exact position of each rail 1 and of each system of fastening of rail 4, and makes it possible to adapt the sleeper-

spacing, as required, to the joints, for the span 2 in question. The method also includes a step of installing the track on the span 2. During this step fixed markings are installed on the span 2 (in the concrete of the span 2) . These markings materialise the axis of the track. More preferably, at each span three markings are made: one at each end and one at the cent advantageous that these markings be installed during the precasting of the span 2 itself. The method includes a step of positioning the track. During this step, dummy rails 5 that have the same profile as those 1 that will be placed on site on this span 2, are arranged on the span 2. The dummy rails 5 are installed on adjusting gauges 6 that make it possible to arrange them in accordance with the position of the final rails. This step is carried out thanks, on the one hand, to the layout drawing that was made beforehand, and, on the other hand, to the markings that were installed beforehand on the span 2. The method further comprises a step of setting up a re-entrant 7 of the systems of fastening 4 of the rails 1 to the span 2 (cf. figure 2). During this step, re-entrant moulds 8 are fixed to the dummy rails 5 (cf. figures 3 and 4). This step, as the step of positioning the track, is carried out thanks to the layout drawing and to the markings on the span 2. It makes it possible to leave free of concrete the zones of the sleeper 3 where the systems of fastening 4 of the rails 1 will be located on site. As such, the re-entrant moulds 8 have dimensions that correspond to those of the systems of

fastening 4 used on site, and they are arranged in the positions provided in these systems 4 . Drawing inspiration from the conventional process of setting up systems of fastening of rails on site, in the curves and connections of a horizontal alignment, in a first step, the re-entrant moulds 8 are fixed to the dummy rail 5 of large radius with the spacing of the sleeper-spacing nominal, and in a second step, the re-entrant moulds are fixed to the dummy rail 5 of small radius by perpendicularity in relation to those fixed to the dummy rail of large radius. In this embodiment the system of fastening 4 used is a system with tie-plate 9: the rail 1 is fixed to the tie-plate 9 (here, by screws 10), and the tie-plate 9 is fixed to the sleeper 3 (here, by sealing rod 11). More precisely, in this example, the system of fastening 4 is the Vossloh system (Vossloh tie-plate 336). Therefore, the dimensions of the re-entrant mould 8 are imposed by those of this system 4. A Vossloh tie-plate 336 measures 390 mm in width and 160 mm in length. Moreover, the length of the sealing rods 11 must also be taken into account as well as their maximal possible inclination which is defined according to the maximal elevation. As such, for a maximal elevation of 120 mm (8.36% for an UIC gauge of 1435 mm), it is necessary to integrate, on either side of the tie-plate 9, a widening of 9.6 mm (rounded to 10 mm). More preferably, the dimensions of the moulds 8 used take into account the tolerances making it possible to adjust the placing of the rails 1 longitudinally, transversally and vertically, in order

to recover from any shifts that could take place when placing the span 2. The longitudinal tolerance includes, other than a tolerance linked to the position of the system of fastening 4 in relation to the span 2 (here, of a value of one inch or 25 mm) , a tolerance linked to the longitudinal position of the span 2 due to the dimension of the joint between two spans 2 (here, of a value of 10 mm). In this example, the dimensions of the mould 8 make it possible to accept a shift of 35 mm in the placing of the system of fastening 4 in one direction as in the other. Therefore the longitudinal dimension of the mould 8 is 230 mm (length of the tie-plate 9 plus twice the longitudinal tolerance). The transversal tolerance concerns the horizontal shift of the placing of the ends of spans 2 in relation to the theoretical axis of the track. It includes, other than a tolerance linked to the position of the system of fastening 4 in relation to the span 2 (here, of a value of one inch or 25 mm), a tolerance linked to the placing of the track (here, of a value of 5 mm). In this example, the dimensions of the mould 8 make it possible to accept a shift of 30 mm in placing the system of fastening in one direction as in the other. Therefore the transversal dimension of the mould 8 is 470 mm (width of the tie-plate 9 plus twice the widening plus twice the tolerance). The vertical tolerance concerns the difference in altitude of the ends of span 2. In this example, the value of the free passage between the finished level of concrete and the bottom of the rail (45 mm in the case

of the Vossloh tie-plate 336) cannot be decreased since this would result in an impossibility of installing the adjusting gauges 6 for placing the track on site. As such, in this example, by considering a tolerance of one inch or 25 mm, the vertical tolerance is 0 in one direction and - 25 mm in the other. The method of precasting further comprises a step of verifying the adjustment of the track at the end of span 2. In order to carry out an adjustment of the rails absolutely outside of the span and to verify the relative values of deflection, and therefore avoid interfacing problems between spans during the placing of the track on site, the dummy rails 5 used have considerable travel. As such, for a span 2 of a length of 25 m, it is preferable to use dummy rails 5 of a minimal length of 45 m in order to have an overhang of 10 m on either side of the span 2. The method of precasting finally includes a step of carrying out sleepers. During this step the armouring of the sleepers 3 are put into place, the formwork 12 is carried out (cf. figures 3 and 4) and the concrete is poured. The transversal and vertical dimensions of each sleeper 3 depend on the system of fastening of the rail 4. As such, for the Vossloh system 336, each sleeper 3 has a minimal height of 200 mm and a minimal width of 525 mm against the tie-plate 9, for a sleeper 3 without anti-derailing measurement. Finally, the method of precasting includes a step of finishing during which the formwork 12, the gauges 6 and the dummy rails 5 provided with re-entrant moulds 8 are removed.

The method of fixing rails 1 on a span equipped with precast sleepers 3 includes a step of preparing the span 2 during which are installed the implantation of the main points of the axis of the tracks (beginning and end of straight alignment, of connection, of body of curve;, of point-end joints of the track devices, etc.) then the secondary points, and during which is carried out the rejection pegging out serving as a reference for the positioning of the track. This method also includes a step of preparing rails 1 during which the rails 1 are welded and provided with systems of fastening 4. As traditionally carried out during the setting in place of systems of fastening of rails on site, in the curves and connections of the horizontal alignment, in a first step, the systems of fastening 4 are fixed to the rail 1 of large radius with the spacing of the sleeper-spacing nominal, and in a second step, the systems of fastening 4 are fixed to the rail 1 of small radius by perpendicularity in relation to those fixed to the rail 1 of large radius. The method includes a step of putting into place rails 1 (cf. figure 7). During this step, the rails 1 are arranged on adjusting gauges 6 which allow them to be arranged in accordance with the course of the track. As required, the method can include a step of formwork during which a formwork is realised around the system of fastening 4 (here, around the tie-plate 9) in order to take into account, where applicable, vertical differences of the position of the rail 1. This necessity is due in particular to the limits imposed on

the vertical tolerances of the dimensions of the re-entrant moulds 8. The method of fixing of rail 1 includes a step of sealing during which the systems of fastening of rail 4 are sealed to the span 2 by concreting in the re-entrants 7 made in the sleepers 3 (and possibly, where applicable, in the formwork carried out around the systems of fastening). Prior to sealing, a final adjustment of the track is carried out. Once the sealing has been carried out, the track is verified. Finally, the method includes a step of finishing during which the gauges 6 and any formwork are removed. This invention is not limited to this embodiment. It can as such be applied to other systems of fastening. It would also be possible to apply it for the precasting of sleepers provided with anti-derailing measurement.

CLAIMS 1. Method of precasting track support sleepers (3) on a precast span (2), characterised in that it includes: - A step of positioning the track during which dummy rails (5) having the same profile as those (1) to be placed on site are arranged on the span (2) in accordance with the position of the final rails (1), - A step of setting up re-entrants (7) of the systems of fastening (4) of the rails (1) to the span (2) during which re-entrant moulds (8) of dimension corresponding to those of the systems of fastening (4) are fixed to the dummy rails (5) , at the positions of the systems of fastening (4), and - A step of realising sleepers (3) during which the armouring of the sleepers are set into place, the formwork (12) is carried out and the concrete is poured. 2. Method of precasting sleepers set forth in claim 1, characterised in that it includes, prior to the step of positioning the track, a step of layout drawing during which is carried out an outline sketch

of the span, of the rails, and of the positions of the systems of fastening of the latter to the span. 3. Method of precasting sleepers (3) set forth in claim 1 or 2, characterised in that it includes, prior to the step of positioning the track, a step of installing the track during which markings are fixed on the span (2). 4. Method of precasting sleepers (3) according to one of claims 1 to 3, characterised in that it includes, prior to the step of concreting, a step of verifying the adjustment of the track at the end of span (2) during which the dummy rails (5) which have an overhang in relation to the span (2), on each side of the latter, are adjusted absolutely outside of the span (2) and have their deflection verified. 5. Method of precasting sleepers (3) according to one of claims 1 to 4, characterised in that it includes a step of finishing during which are removed the formwork (12), the gauges (6) and the dummy rails (5) provided with re-entrant moulds (8). 6. Method for laying rails (1) on a. span (2) provided with precast sleepers (3) comprising re-entrants (7), characterised in that it includes: - A step of setting up rails (1) during which the rails (1), provided with their systems of fastening (4), are correctly arranged in relation to the span (2), and - A step of sealing during which the systems of fastening (4) are sealed to the span (2) by concreting in the re-entrants (7) made in the sleepers (3). 7. Method for laying rails (1) set forth in claim 6, characterised in that it includes, prior to the step

of setting up the rails (1), a step of welding during which the rails (1) are welded to the rails of the preceding span. 8. Method of placing rails (1) set forth in claim 6 or 7, characterised in that it includes, prior to the step of fastening, a step of formwork during which a formwork is carried out around the systems of fastening (4) . 9. Method for laying rails (1) on a precast span (2), characterised in that it includes the steps of the method of precasting sleepers (3) according to one of claims 1 to 5, a step of supplying during which the span (2) provided with precast sleepers (3) is brought to a project site, and the steps of the method for laying rails (1) on the precast span provided with precast sleepers (3) in accordance with one of claims 6 to 8.

The method includes: - A step of positioning the track during which dummy rails (5) having the same profile as those to be placed on site are arranged in the span (2) in accordance with the position of the final rails, - A step of setting in place re-entrants of the systems of fastening rails to the span (2) during which re-entrant moulds (8) of dimension corresponding to those of the systems of fastening are fixed to the dummy rails (5), at the positions of the systems of fastening, and A step of realising sleepers during which the armouring of the sleepers are set into place, the formwork (12) is carried out and the concrete is poured.

Documents

Sign in to open
Orders
Section
Application documents
1 abstract-519-kol-2009.jpg 06 Oct 2011
2 519-kol-2009-specification.pdf 06 Oct 2011
3 519-KOL-2009-PRIORITY DOCUMENT.pdf 06 Oct 2011
4 519-kol-2009-gpa.pdf 06 Oct 2011
5 519-kol-2009-form 5.pdf 06 Oct 2011
6 519-kol-2009-form 3.pdf 06 Oct 2011
7 519-kol-2009-form 2.pdf 06 Oct 2011
8 519-kol-2009-form 1.pdf 06 Oct 2011
9 519-kol-2009-drawings.pdf 06 Oct 2011
10 519-kol-2009-description (complete).pdf 06 Oct 2011
11 519-kol-2009-correspondence.pdf 06 Oct 2011
12 519-KOL-2009-CORRESPONDENCE-1.1.pdf 06 Oct 2011
13 519-kol-2009-claims.pdf 06 Oct 2011
14 519-KOL-2009-ASSIGNMENT.pdf 06 Oct 2011
15 519-KOL-2009-ANEXURE TO FORM 3.pdf 06 Oct 2011
16 519-kol-2009-abstract.pdf 06 Oct 2011
17 519-KOL-2009-FORM-18.pdf 01 Mar 2012
18 519-KOL-2009-FER.pdf 11 Jan 2018
19 519-KOL-2009-Verified English translation (MANDATORY) [10-04-2018(online)].pdf 10 Apr 2018
20 519-KOL-2009-Information under section 8(2) (MANDATORY) [16-04-2018(online)].pdf 16 Apr 2018
21 519-KOL-2009-PETITION UNDER RULE 137 [30-06-2018(online)].pdf 30 Jun 2018
22 519-KOL-2009-OTHERS [30-06-2018(online)].pdf 30 Jun 2018
23 519-KOL-2009-FER_SER_REPLY [30-06-2018(online)].pdf 30 Jun 2018
24 519-KOL-2009-DRAWING [30-06-2018(online)].pdf 30 Jun 2018
25 519-KOL-2009-COMPLETE SPECIFICATION [30-06-2018(online)].pdf 30 Jun 2018
26 519-KOL-2009-CLAIMS [30-06-2018(online)].pdf 30 Jun 2018
27 519-KOL-2009-ABSTRACT [30-06-2018(online)].pdf 30 Jun 2018
28 519-KOL-2009-HearingNoticeLetter-(DateOfHearing-13-03-2020).pdf 06 Feb 2020
29 519-KOL-2009-Response to office action [17-02-2020(online)].pdf 17 Feb 2020
Search strategy
1NewMicrosoftOfficeWordDocument(2)_09-01-2018.pdf